The Emirati state-owned renewables developer Masdar has begun construction on a giant solar-plus-storage project in Abu Dhabi.

The roughly AED232 billion (US$5.9 billion) project combines 5.2GW of solar PV with a 19GWh battery energy storage system (BESS), which Masdar claimed was the “largest and most technologically advanced system of its kind in the world.”

The project is expected online in 2027. Developed alongside the Emirates Water and Electric Company (EWEC), the project will be capable of delivering 1GW of baseload energy around the clock, Masdar said. The company claimed the site will “overcome intermittency” and produce baseload, round-the-clock energy at “a globally competitive tariff”. “Round-the-clock” facilities are already being built and contracted elsewhere, though rarely at this scale.

Masdar claimed the project features “cutting-edge technologies”, including a virtual power plant (VPP), grid-forming and black start capabilities and AI-enhanced forecasting and intelligent dispatch. It will reportedly provide power to the AI sector, potentially to data centres, though comments from EWEC CEO, Ahmed Ali Alshamsi, did not clarify any specific offtakers or facilities:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Abu Dhabi and the UAE are a global hub for artificial intelligence research, innovation, and adoption, and this project will ensure that the energy needs of this key sector are met sustainably, powering the next generation of economic growth,” Alshamsi said.

“This gigascale project is a step towards redefining the role of renewable energy for the information age,” said Sultan Al Jaber, chairman of Masdar, head of the Abu Dhabi National Oil Company (ADNOC) and Emirati minister of industry and advanced technology.

In January, Masdar announced supply deals with Chinese solar manufacturers JA Solar and Jinko Solar to supply the 5.2GW site’s PV modules, and POWERCHINA and India’s Larsen & Toubro are the project’s preferred engineering, procurement, and construction (EPC) contractors. Chinese energy storage firm CATL will supply the BESS for the site, providing its newest 6.25MWh solution, Tener, for the full 19GWh capacity of the project, as covered by Energy-Storage.news in January.

7 April 2026
Dubai World Trade Centre, Dubai
Co-located with the extremely well renowned Middle East Energy Show, join us for the inaugural Energy Storage Middle East Summit in Dubai, April 2026, as we bring our world leading energy storage series to one of the world’s fastest-growing BESS markets. This landmark event will explore the Middle East’s trajectory to become the third largest storage market globally by 2026, with a special focus on the region’s ambitious renewable energy targets and BESS integration strategies.

Read Next

February 9, 2026
Chinese battery manufacturer EVE Energy has secured a contract with the Malaysian government to deploy an AC/DC integrated 36MWh solar-plus-storage system at Kuala Lumpur International Airport (KLIA).
February 9, 2026
State-owned energy company Synergy has completed the 500MW/2,400MWh Collie Battery Energy Storage System (CBESS) in Western Australia, establishing Collie as home to Australia’s largest operational battery energy storage system (BESS).
February 4, 2026
“Standalone solar is not dead, but it is challenging,” said Pierre Bartholin, head of power hedging at investor Nuveen Infrastructure, opening the debate at Solar Media’s Solar Finance Investment Europe (SFIE) conference in London on the future of co-located battery storage. 
February 3, 2026
Tonic Group has received federal environmental approval for a 440MWh solar-plus-storage facility in Western Australia in less than a month.
January 30, 2026
Battery energy storage projects have emerged as the dominant force in Australia’s energy investment landscape, accounting for 46% of the nation’s 64GW development pipeline, according to the Australian Energy Market Operator’s (AEMO) latest quarterly report.