System-level issues account for nearly half of BESS production defects, says CEA

LinkedIn
Twitter
Reddit
Facebook
Email
Chart showing the frequency of system-level issues for battery energy storage systems.
Nearly half of the issues detected by the CEA came at the system level with Fire Suppression System and Thermal Management System with a high percentage. Chart: Clean Energy Associates.

A recent report from the Clean Energy Associates found that system-level issues accounted for nearly half of all defects found in battery energy storage systems (BESS), of which two issues related to increased risk of fire.

In its report, BESS Quality Risks, the CEA conducted quality audits on over 30GWh of lithium-ion energy storage projects over the past six years, with more than 1,300 manufacturing issues identified.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Of these issues identified, almost a third (26%) of BESS units inspected by the CEA had defects in the Fire Suppression System, while 18% of units had Thermal Management System defects, both of which are critical for functional safety, as defects in these systems can lead to increased risk of fire.

Some of the problems detected were a non-responding release actuator for the fire extinguisher agent, which, if malfunctioning, could potentially allow the fire to propagate further; non-responding smoke and temperature sensors, which wired incorrectly, could prevent the smoke sensor from detecting the presence of smoke within the system.

In the US, New York has been one of the leading states in its approach to safety issues regarding fires and earlier this month recommended changing the state fire code to better manage risks associated with battery storage systems installed in the state.

Moreover, an industry-led initiative from the American Clean Power Association (ACP) recently published a battery safety incident guide for first responders. Whereas in California, the state passed legislation last year that requires BESS owners to put in place safety and communications protocols with first responders and other key stakeholders.

Half of the issues came from system-level

These two issues – Fire Suppression System and Thermal Management System – were among the highest defects detected in the system integration of a BESS. Despite much of the industry’s attention being on cell selection, system-level should not be overlooked, as a potential source of problem, since these represent nearly half of (48%) the defects found by CEA.

A higher level of system-related issues is due to two reasons, the first is due to the BESS integration process being mostly manual and labour-intensive, while the second is problems originating from defects in upstream components might not have been caught in earlier quality checks.

Within that category, balance of system (58%) and enclosure (34%) had the majority of system-level findings. Although only 8% of the findings came from performance test, these had larger and more complex issues associated with them.

Recently, Energy-storage.news hosted a webinar with the CEA presenting some of the most common issues seen in the factory, their typical root causes and steps that can be taken in the manufacturing process to prevent these issues. During the webinar, George Touloupas, senior director of technology and quality, solar and storage at CEA, explained that the reason why the report focused on lithium-ion batteries was because: “Nobody is buying anything else than lithium-ion.”

One of the key takeaways from the report was that “quality assurance is the most efficient means to mitigate risks during mass productions,” added Touloupas.

Cell and module issues

Despite a higher automation process, cell issues represent 30% of the CEA’s issues found, with a third of the incidents occurring during electrode manufacturing, 38% during cell assembly and 30% during cell finishing.

The last category was for the module which represented 23% of the total findings, which is largely due to production lines being more manual. Half of the issues were related to interconnection wielding. This is due to the manual aspect of it and a lack of efficient quality control procedures.

For more details on issues related to each category, the report can be accessed here.

3 June 2025
Stuttgart, Germany
Held alongside the Battery Show Expo Europe in Stuttgart, Energy Storage Germany spotlights Germany’s rapid ascent in the European storage sector. Once driven by residential demand, utility-scale projects are now surging, with 184 MW added across 44 projects in 2023. With nearly 16 GWh of capacity installed in the first half of 2024, Germany is set to integrate 24 GW of utility-scale energy storage by 2037, creating substantial opportunities.
11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

March 14, 2025
A news roundup focusing on system integrator Powin’s recent moves in the industry, resource updates in New Mexico and a newly announced energy management system from Prevalon.
March 13, 2025
Developer Cypress Creek Renewables has received a US$133 million financing from First Citizens Bank for the Destiny Storage Project, a standalone battery energy storage system (BESS) in Texas.
March 13, 2025
Carlyle Portfolio Company-owned developer Copia Power has closed a US$1.71 billion debt facility to fund construction of its Maricopa Energy Centre Projects.
March 13, 2025
Billion Watts Technologies, the solar and energy storage subsidiary of Taiwan’s Billion Electric, has completed a 64MW/262.43MWh battery energy storage system (BESS) in central Taiwan.
March 13, 2025
Ark Energy has penned a battery supply agreement with Hanwha Energy for a 275MW/2,200MWh BESS in northern New South Wales, Australia.

Most Popular

Email Newsletter