Solar Philippines working on Asia’s ‘largest solar, diesel, battery micro-grid’ without subsidies

August 23, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
Solar Philippines founder and CEO Leandro Leviste aims to replicate this system with many more projects all without subsidies. Image: Solar Media.

Filipino renewable energy firm Solar Philippines is developing an off-grid solar, battery and diesel micro-grid in the Philippines that could be the largest of its kind in Asia, according to the company head.

Solar Philippines founder and CEO Leandro Leviste told Energy-Storage.News that the micro-grid system on the island of Mindoro will include an 8MWh energy storage battery, a 4MW solar PV plant and diesel capacity – enough to power a whole town.

Leviste added: “We are going to be replicating a lot of these that are unserved, without subsidies and without any government programmes. So we are doing all on a deregulated basis.”

He also gave new details about the nation’s first utility-scale solar plant combined with storage at Concepcion,Tarlac, which the company started constructing in March. While it was already known that the PV project would be 150MW, Leviste revealed that the storage element would include a 50MWh battery. Commissioning is due in the next few months, he added.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Solar Philippines claims that this was in fact the first project to start construction after the government’s Feed-in-Tariff (FiT) programme came to an end, under President Duterte’s administration.

Today, Duterte was present to inaugurate the newly expanded Solar Philippines solar module factory at Batangas – the first such facility in the Philippines – that now has 800MW capacity.

Read Next

January 19, 2026
FranklinWH and ConnectDER have had their respective battery and electric meter technologies enrolled into programmes in Arizona expected to accelerate the take-up of home batteries for virtual power plants (VPPs).
January 16, 2026
Duke Energy, Elevate Renewables, and Fluence Energy, along with BrightNight and Cordelio Power, are advancing BESS projects across the BESS.
January 15, 2026
ASL has launched a consultation on a new Hybrid Generation LTESA product alongside its 2026 NSW Consumer Trustee Investment Priorities.
January 9, 2026
Jointly owned by Masdar and Igneo Infrastructure Partners, independent power producer (IPP) Terra-Gen’s Lockhart CL I and II battery energy storage system (BESS) projects have reached commercial operations in San Bernardino County, California, US.
January 9, 2026
Yanara has appointed Gamuda Australia as the project delivery partner for the early contractor involvement (ECI) phase of the Mortlake Energy Hub in Victoria.