Scatec signs PPAs for co-located solar with 1.1GWh storage in South Africa

LinkedIn
Twitter
Reddit
Facebook
Email

Renewable energy power producer Scatec has signed power purchase agreements (PPA) for three co-located solar and storage projects with 1.1GWh of energy storage in South Africa.

The Norway-based company has signed the PPAs for the three Kenhardt projects in Northern Cape. The projects are providing dispatchable energy resources to grid operator ESKOM to help reduce shortfalls in capacity on the grid, procured under the Risk Mitigation Independent Power Producer Procurement Programme (RMIPPPP).

Scatec’s three projects, which pair 540MW of solar PV with 1.1GWh of battery energy storage system (BESS) capacity, will provide 150MW of dispatchable energy from 5 a.m. to 9.30 p.m. The BESS will enable the flexible dispatch of energy and allow ESKOM and Scatec to reduce the size of the grid connection needed to integrate the new resources.

The company’s announcement does not spell out the power of the BESS, while an announcement last year when it was awarded preferred bidder status said it would be a 225MW system.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

They are the only fully renewable resources awarded PPAs under the RMIPPPP tender, and will provide power under a 20-year agreement. Scatec will cover all engineering, procurement and construction (EPC), operation & maintenance (O&M) and asset management services for the project.

Financial close is expected within 60 days of the PPA signature date (2 June) and construction will begin thereafter although an expected commissioning date hasn’t been revealed. When Scatec was awarded preferred bidder status, the resources were expected to be up and running by the middle of this year.

Scatec will own 51% of the equity in the project while H1 Holdings, its local Black Economic Empowerment (BEE) partner will own the remaining 49%. BEE is a government programme to facilitate broader participation of the black population in the economy to redress the lingering inequalities of apartheid. Standard Bank Group was lead arranger and debt provider.

Gas resources were the big winner in RMIPPPP, although up to 430MW/1,300MWh of energy storage was successful according to consultancy Clean Horizon’s analyst Corentin Baschet. The South African government is seeking to add more storage to the grid through other programmes too.

A separate programme by ESKOM, the Renewable Energy IPP Procurement Programme (REIPPPP), is solely for renewable energy resources and the two programmes together are expected to add about 1GW of storage to the South African grid.

Some 200MW/832MWh of standalone BESS projects at eight sites through REIPPPP were in final stage pre-contract discussions in March this year. And an even bigger round of procurement is expected to start in the next few months, Adam Terry, technical director at Harmattan Renewables, which is working with IPPs on projects in the country, said in a recent interview with Energy-Storage.news.

The standalone assets will provide national peak shaving services for four hours a day plus ancillary services and local support, Eskom said.

8 September 2026
Barcelona, Spain
Battery & Energy Storage Tech Europe (BESTE) is Europe’s industrial scaling platform for stationary and industrial battery applications — not EVs. Taking place 8–9 September 2026 at Fira de Barcelona, BESTE brings together utilities, IPPs, energy-intensive industries, data centres, ports, rail, maritime, defence and aerospace OEMs — all deploying or integrating battery storage at scale. Over 100 companies already confirmed — including EDP Renewables, Acciona, Endesa, Naturgy, Neoen, Galp, Basquevolt and Veolia — alongside 40+ expert speakers and international institutional support from BEPA, BVES, LDES and Volta Foundation. Where Europe’s battery & ES ecosystem turns projects into reality.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

July 29, 2026
NextEra Energy recorded a 9.5% increase in its net earnings in Q2 2026, as the company advanced its plan to merge with Dominion Energy to form the world’s largest regulated power utility.
July 29, 2026
Utility Georgia Power has completed construction of the 49.5MW/198MWh Moody Battery Facility, located outside of Valdosta, Georgia, US.
July 29, 2026
NEM-wide battery price spreads fell 85% in a single year to average AU$51/MWh (US$35/MWh) in Q2 2026, according to AEMO.
July 29, 2026
Quinbrook has completed construction and commenced commercial operations at Stage 2 of its Supernode BESS in Australia.
Sponsored
July 28, 2026
We caught up with Kevin Huang, Senior Vice President and President of Energy Storage Product Line at Envision Energy at Smarter E in Munich for a video interview on the company’s energy storage strategy and the growing role of AI data centres in power demand.