Samsung C&T submits 300MWh solar-plus-storage site to Australia’s EPBC Act

September 29, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Samsung C&T Renewable Energy Australia has submitted plans for a 300MWh solar-plus-storage project in Queensland to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act.

The Dunmore Solar Farm and battery energy storage system (BESS) will be constructed on a 534-hectare portion of a larger 1,056-hectare site at Cecil Plains Moonie Road, located roughly 240km west of the state capital, Brisbane.

It will consist of a 300MW solar PV power plant co-located with a 2-hour duration 150MW/300MWh BESS, which will be installed on a concrete pad adjacent to site offices and operational areas.

According to documents submitted as part of the EPBC Act application, the Dunmore development includes a new 330kV switchyard between Braemar and Bulli Creek Substation, with a proposed Dunmore substation occupying a 300m x 300m area.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Construction of the Dunmore project is scheduled to commence in July 2027 and will involve several distinct phases. 

The initial site preparation will include clearing and grubbing of vegetation, followed by civil works to establish access roads, drainage systems, and foundations for both the solar arrays and BESS infrastructure. The construction team will install approximately 600,000 solar modules mounted on the single-axis tracking system.

Specifically, the site will use Horizontal Single-Axis Solar Tracking (HSAT) PV modules to maximise energy capture throughout the day. Power conversion units consisting of inverters and step-up transformers will convert DC electricity from the solar modules to high-voltage AC for efficient transmission to the substation.

Meanwhile, the BESS deployment will involve specialised electrical and mechanical contractors installing the battery modules, inverters, transformers, and associated control systems.

Samsung C&T estimates that the construction phase will create approximately 150 jobs over a 12-18-month period. The project is expected to be fully operational by early 2029, aligning with the planned grid connection date.

Once complete, the project will provide long-term renewable energy generation and storage capacity to the National Electricity Market (NEM), which spans Australia’s eastern and southern states and territories.

The development has already received approval from Toowoomba Regional Council following a public notification period during which no submissions were received.

This development follows Samsung C&T’s growing portfolio of Australian energy storage projects. The company recently submitted plans for a 100MW/400MWh BESS in Western Australia and an 80MW/320MWh system in New South Wales to the EPBC Act.

400MWh solar-plus-storage project submitted to Australia’s EPBC Act

In other news, developer ACE Power and Osaka Gas Energy Australia have submitted plans for a 100MW solar-plus-storage project to the EPBC Act.

The Narrabri Solar Farm project, which is set to be developed under a special purpose vehicle called Narrabri Solar Power, includes a co-located 100MW/400MWh battery energy storage system (BESS) and will connect to the National Electricity Market (NEM).

The development is situated roughly 410km northwest of the New South Wales capital, Sydney, within the Narrabri Shire Local Government Area. It covers a site of 314 hectares, with construction scheduled to commence in February 2027.

The initial phases will involve site establishment, which includes installing piles to support the solar modules driven 1.5 to 2.5 meters into the ground. Additionally, the project will include constructing internal access tracks, preparing the substation bench and installing security infrastructure.

According to the EPBC Act documents, the construction phase is expected to last approximately 18 months, with peak construction activities concentrated in a 12-month period.

The operational phase is projected to extend for 30 years until 2058, after which decommissioning will occur with commitments to return the site to a safe, stable and non-polluting state capable of sustaining pre-solar PV power plant agricultural land uses.

24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

November 28, 2025
The Australian government has officially opened CIS Tender 8, targeting 16GWh of energy storage capacity across the NEM.
November 27, 2025
The Western Australian government has launched the first stage of an Expression of Interest (EOI) process for a 50MW/500MWh vanadium flow battery energy storage system (VBESS) in Kalgoorlie.
Premium
November 26, 2025
Energy-Storage.news Premium speaks with Michael Kirschner, Managing Director, US, for Habitat Energy, about optimising BESS projects in ERCOT.
November 26, 2025
Potentia Energy has received federal environmental approval for its 1,000MWh Tallawang Solar Hybrid project, and Fluence has delivered its Gridstack battery energy storage equipment to Ampyr Australia’s 600MWh Bulabul Battery installation.
Sponsored
November 26, 2025
As Australia accelerates its transition toward renewables, demand for reliable & sustainable energy storage solutions has never been higher.