Utility SCE awards 38.5MWh of ESS projects as ‘non-wires alternative’ to network upgrades

October 22, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
Image: EsVolta.

Four energy storage projects that have been proposed as an alternative to expensive transmission and distribution (T&D) network upgrades, totalling 38.5MWh of capacity have been awarded to developer EsVolta by California utility Southern California Edison (SCE).

Subject to approval by the California Public Utilities Commission (CPUC), the four projects are in the counties of Riverside and Ventura and comprise of the 3MW / 12MWh Wildcat Energy Storage Project near Palm Springs and three projects dubbed Acorn Energy Storage, which together make up 6.5MW / 26.5MWh of energy storage capacity. If approved, the projects would be scheduled for completion by March 2020.

In 2017, SCE had issued a Request for Offers, the Integrated Distributed Energy Resources RFO. Seeking to deploy capacity resources at strategic locations along the utility’s distribution network, SCE hopes to avoid needing to keep upgrading the distribution system to accommodate load growth, while enhancing network reliability.

EsVolta claims to have over 450MWh of energy storage projects either already in operation or under development and seeking utility off-takers, plus a further pipeline of “approximately 2,000 MWh of additional development stage projects”. This includes the 75MW / 300MWh Hummingbird Energy Storage project for another California utility, Pacific Gas & Electric (PG&E), which is one of those currently under development.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In a February 2018 technical feature article, first published in our quarterly journal PV Tech Power and later reproduced on this site, Alex Eller, research analyst and senior consultant at Navigant Research, discussed the coming phenomenon of so-called ‘non-wires alternatives’ to T&D infrastructure investment.

“The new generation of less expensive and more intelligent distributed energy resources (DER) and energy storage technologies located on both the T&D grid and customers’ properties has opened the door to a compelling array of new options for how to best utilise existing infrastructure.

“These technologies will disrupt the conventional T&D industry by maximising the value and efficiency of existing grid assets while empowering customers to participate in the management of the grid,” Eller wrote.

Read Next

November 25, 2025
Texas-based IPP Vistra Energy has informed the California Energy Commission (CEC) that it will not be advancing its 600MW Morro Bay battery energy storage system (BESS).
November 24, 2025
Fluence, Energy Dome and EDF each scored consecutive wins in prestigious categories at the Energy Storage Awards 2025 in London.
Premium
November 21, 2025
The Community Development and Infrastructure Department at Santa Cruz County has become the latest California jurisdiction to publish a draft zoning ordinance regulating the deployment of battery energy storage systems. 
November 20, 2025
From the US, Maxwell Technologies is acquired for its third time, by Clarios, Fullmark Energy completes a tax credit transfer, and OATI partners with Colville Tribes on microgrid solutions.
Premium
November 19, 2025
An energy storage agreement (ESA) between Toronto, Ontario-headquartered developer Hydrostor and California community choice aggregator (CCA) Central Coast Community Energy (3CE) is set to be amended for the third time.