Steag inaugurates US$100 million largest-of-its-kind energy storage system

November 18, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

Credit: Steag
Major German utility Steag and automation company Nidec ASI, formerly known as Ansaldo Sistemi Industriali, have inaugurated a 90MW energy storage system in Germany, in what is the largest installation of its kind.

The project consists of six 15MW Nidec ASI storage systems that aid Steag in the stabilisation of the country’s grid via frequency regulation and voltage control.

Germany’s largest battery system was celebrated in an inauguration ceremony held in Duisburg-Walsum, attended by North-Rhine Westphalia minister of Economic Affairs Garrelt Duin and Saarland’s Minister President Annegret-Kramp-Karrenbauer. During the ceremony, the select systems were officially put into operation at the Weiher power plant.

This monumental project has been a long time in the making, with Steag commissioning Nidec in November 2015 to supply and install the systems that use Korea’s LG Chem batteries. The project, that reportedly cost around US$100 million, broke ground last May and subsequently installed six energy storage systems at different sites including Weiher, Bexbach and Fenne.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Six lithium-ion battery-based systems were deployed in North-Rhine Westphalia, in the northwest of the country and in Saarland, in the south, three in each region.

“The battery storage system makes an important contribution to the energy turnaround,” said Duin at the ceremony. “On the one hand, it stabilizes the power grid and increases supply security; on the other hand, emissions are reduced by saving fossil fuels. In the current energy environment with a high dynamics of change, we welcome the investments made by STEAG, especially in view of the fact that the project is implemented without subsidies. It shows that good ideas can be developed to market quickly with decisive action “.

“The grid stability and security of supply inherent are currently the most important criteria for the success of the energy transition,” commented Joachim Rumstadt, CEO of Steag. “Due to the ever-increasing share of volatile electricity from renewable energies, the electricity network is becoming increasingly stressed. I am proud that the large battery system is not only a technological pioneer, but that our investment has also been fully implemented on the market, without public funding. “

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

Premium
April 8, 2026
A panel at the 2026 US Energy Storage Summit in Dallas, Texas, discussed the “creative, innovative structures” developers are having to embrace to secure long-term revenues for energy storage projects.
April 8, 2026
The Canadian Province of Prince Edward Island’s PEI Energy Corporation (PEIEC) has issued a request for expressions of interest (REOI) for a 10-50MW, four-hour duration battery energy storage system (BESS).
April 7, 2026
Quebec-based IPP Boralex and Six Nations of the Grand River Development Corporation (SNGRDC) have announced the closing of a CA$202 million (US$145.12 million) financing for a 125MW/500MWh battery energy storage system (BESS) in Oxford County, Ontario, CA.
Premium
April 7, 2026
The project represents a US$128.6 million investment and is scheduled to begin construction this year, with commercial operations commencing in December 2026.
April 7, 2026
IPP Neoen will start construction on large-scale BESS projects in France and Japan in the coming months.