South Africa’s Eskom opens tender for 80MW / 320MWh battery storage

August 3, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Sere Wind Farm in Western Cape, where the substation set to host the battery project is located, achieved commercial operation in 2015. Image: Eskom.

Eskom, the state-owned electricity utility of South Africa, has begun tendering for a battery energy storage system (BESS) of minimum size and capacity 80MW / 320MWh.

The utility issued a procurement notice at the end of July requesting bids for the Eskom Investment Support Project and Eskom Renewables Support Project. The twin project calls for interested parties to design, engineer, supply, construct, test and commission a battery energy storage system “with a minimum of 80MW / 320MWh usable capacity”.

The winning bidder will also be responsible for providing five years of operations and maintenance (O&M) services for the project, to be built at Skaapvlei Substation, in the town of Vredendal in the Republic of South Africa’s Western Cape province.

Eskom would like the development process to be complete within nine months for the project, for which the utility has received financing from the World Bank, African Development Bank and New Development Bank. Funds received will be used directly to pay for the BESS’ deployment.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Sealed bids are being invited, with Eskom using international competitive procurement processes using Request for Bids – this is in line with World Bank requirements for borrowing funding. The Skaapvlei substation is near the 100MW grid-connected Sere Wind Farm and an initial site meeting is being held at that wind farm on 20 August. The bidding process closes in September.

The project looks to be an important step towards Eskom meeting a 1,400MWh energy storage target set out by the utility in a 2018 long-term resource plan to add system reliability as well as integrate renewable energy facilities onto the grid.

Read Next

October 17, 2025
Utility and power firm Naturgy has started building its first BESS projects in Spain, at four solar PV plants in Almeria and the Canary Islands.
October 15, 2025
A flurry of grid-scale BESS project progress totalling more than a combined 1.5GWh in the past week, from Renalfa in Bulgaria, Engie in Romania, Nala Renewables in Finland and Metlen in Greece.
October 15, 2025
Takeaways from the first day of Energy Storage Summit Latin America 2025, including the Chilean and Argentinian markets.
October 14, 2025
Developer Epic Energy has commenced commercial operations at its 100MW/200MWh Mannum battery energy storage system (BESS) in South Australia.
October 13, 2025
Queensland’s Energy Roadmap 2025 suggests that by 2030, up to 4.3GW of short-duration energy storage could be operational.

Most Popular

Email Newsletter