Updated 27 July 2021: An RWE spokesperson told Energy-Storage.news that the combined capacity of the BESS installations will be 128MWh across the two sites. It was also confirmed that the project will be commercially-oriented, rather than a demonstration of the technology or potential business models with the two systems mainly providing “balancing energy” for the grid and “therefore geared towards the FCR (Frequency Containment Reserve) market,” the spokesperson said.

RWE has announced the construction of two battery energy storage systems (BESS) in Germany which will be “virtually coupled” with existing run-of-river hydroelectric power plants.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The Essen-headquartered power generation company said on 22 July that it will install 117MW of batteries at the two sites: 45MW of BESS at its Gersteinwek power plant in Lingen, Lower Saxony and 72MW at Emsland power station in Werne, North Rhine-Westphalia. The battery projects will require an investment of around €50 million (US$59 million) and are scheduled to go into action at the end of 2022.

RWE said the battery systems can be used to raise or decrease the flow-through of power at the hydropower plants, increasing the effective capacity available to be put into electricity system balancing markets. The hydroelectric generation adds about 15% extra capacity to the battery systems, with their primary application being to help maintain the grid’s operating frequency.

Energy-Storage.news has reported on a small handful of other projects around the world that pair batteries with run-of-river hydropower. These include three in Sweden: a 5MW / 6.2MWh BESS at the 44MW Forshuvud hydropower station, installed in 2019 by the power plant’s owner Fortum ,and two battery storage system projects of 6MW and 9MW from technology provider Nidec ASI at hydropower plants in Edsele and Lövön by E.On’s energy supplier subsidiary Uniper which are currently underway. Like RWE’s two new projects, these will also be providing frequency regulation services.

“Large battery storage systems in the megawatt category make a key contribution towards network stability in the new energy world. The implementation of this project at a power station with a tradition as long as Werne’s demonstrates impressively how competence and innovative technologies can be used to design the secure energy supply of the future,” North-Rhine Westphalia state minister for economic affairs and energy Andreas Pinkwart said.

“The Lingen power plant is a role model for the energy transition. It’s impressive how quickly the transformation from conventional electricity generation to a state-of-the-art, environmentally friendly energy world is progressing,” Olaf Lies, Lower Saxony state minister for environment, energy, building and climate protection said.

Read Next

July 16, 2025
The Federal Court of Justice in Germany has rejected an appeal against BESS being eligible for the BKZ construction fee, a decision which means potentially millions more in costs for building projects in the country.
July 16, 2025
Two US-headquartered solar and sustainability-focused investors have launched GSSG Chikuden, a utility-scale battery storage developer, in Japan.
July 15, 2025
Utility and power firm Verbund has selected system integrator Fluence to deploy two BESS projects in Germany totalling 186MWh of capacity, with noise and cybersecurity standards a key part of the selection process.
July 11, 2025
The Victoria government has launched the third round of its 100 Neighbourhood Batteries Program, allocating AU$6.6 million (US$4.34 million).
July 11, 2025
Allegro Energy, an Australian-based developer of water-based redox flow battery energy storage solutions, has claimed its microemulsion flow battery (MeFB) could be tailored to support the “exponential growth” of data centres.

Most Popular

Email Newsletter