PSE&G installs, commissions 1MWh battery system for microgrid project in New Jersey

By Conor Ryan
LinkedIn
Twitter
Reddit
Facebook
Email
Eos Energy Storage grid-scale system. This and cover image: Eos Energy Storage.

Eos Energy Storage has installed and commissioned a 1MWh Eos Aurora battery system at a wastewater treatment plant in Caldwell, New Jersey.

This system will serve as a main component of utility Public Service Electric and Gas Company's (PSE&G) on-site energy storage microgrid that will help keep the facility operational during extended power outages.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The microgrid system includes an Eos Energy Storage system, along with an 896kW solar PV system designed and installed by Advanced Solar Products. Siemens Energy Management integrated the Eos Aurora system, solar facility, and existing diesel generator — utilising Eos Znyth technology as the base of the microgrid. Znyth use zinc hybrid cathodes, which Eos claims makes its batteries 30% to 40% lower cost than comparable lithium-ion systems.

The company is shipping its systems this year for US$160 per kWh and once it scales up into larger utility-scale systems, Eos says it could give solar-plus-storage projects an LCOE of below 10 cents per kWh. Utility Engie is testing Eos Znyth batteries, stacked into Eos' 'Aurora' branded grid-scale systems, in Brazil, while Eos also has an agreement to collaborate with engineering giant Siemens on developing energy storage systems with AC power conversion and controls.

The Caldwell wastewater treatment plant microgrid stands as part of a 3MW portion of PSE&G's Solar 4 All program — a plan that looks to develop projects that mesh solar with other technologies to strengthen the electricity grid.

Todd Hranicka, director of solar energy at PSE&G, said: “One of the goals of our Solar 4 All program is to help support the growth and development of solar and related industries in New Jersey. So we were especially happy to include the battery technology from a fellow New Jersey company like Eos into a project that helps make our electric system and a piece of critical infrastructure more reliable and resilient.”

Construction of the storage system was a joint undertaking between Advanced Solar Products, Eos, and Siemens Energy Management.

Michael Oster, CEO at Eos, said: “The Caldwell project is truly a landmark for us. It shows that municipalities and utilities are embracing large-scale, long-duration energy storage in a manner that will greatly enhance public safety and grid resiliency. We are proud to partner with these industry leaders and look forward to setting new standards for energy reliability and cost effectiveness.”

Read Next

July 8, 2025
Developer and independent power producer (IPP) Recurrent Energy, subsidiary of Canadian Solar, announced commercial operation of its 1,200MWh Papago Storage facility in Maricopa County, Arizona.
July 7, 2025
Avantus has raised more than US$500 million for 200MW/500MWh Aratina 1 BESS project in Kern County, California.
July 4, 2025
Zinc hybrid cathode battery and storage system maker Eos Energy has received its second loan advance from the US Department of Energy’s (DOE’s) Loan Programs Office (LPO).
July 3, 2025
In Texas, Vitis Energy announces financial close of the Apache Hill Energy Centre while Enertis Applus+ provides independent engineering services for Excelsior Energy Capital.
July 3, 2025
Idaho Power’s updated integrated resource plan adds more solar, wind and energy storage than gas generation, while Public Service Company of New Mexico gets 450MW of solar and storage added to its resource application.

Most Popular

Email Newsletter