Landis+Gyr joins E.ON on 10MW Arizona storage facility project

August 2, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

Swiss smart metering firm Landis+Gyr is to supply a 10MW energy storage system to Tucson Electric Power (TEP), a utility in Southern Arizona.

Landis+Gyr is supplying E.ON Climate & Renewables (EC&R), an arm of the European utility, which is handling the construction of the TEP storage facility.

TEP struck long-term arrangements with EC&R and wholesale electricity supplier NextEra Energy last year to supply capacity and availability from two new 10MW energy storage systems, to help balance load and regulate frequency on its distribution system.

The Arizona Corporation Commission (ACC) approved the projects in May.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The EC&R storage facility, located at the University of Arizona Science and Technology Park southeast of Tucson, is accompanied by a 2MW solar array. It is expected to be completed in the first quarter of 2017.

Landis+Gyr is supplying a containerised Li ion energy storage system that integrates Toshiba’s SCiB lithium titanate oxide batteries.

Mike Cooper, general manager of distributed generation and energy storage at Landis+Gyr, said: “The TEP storage project is driven by the growing need for rapid response to changes in energy supply and demand. This battery solution will allow E.ON to provide a flexible, high availability service to TEP for maintaining high quality and reliable power delivery in its territory.”

TEP, with around 420,000 customers in Arizona, is looking at ways to integrate a growing portfolio of renewable generating resources, with a goal of generating 30% of its power, or 1,200MW, from renewable resources by 2030.

Read Next

April 21, 2026
New Zealand generator-retailer Genesis Energy has reached Final Investment Decision (FID) on the second stage of its Huntly battery energy storage system (BESS).
April 20, 2026
Pacific Energy has been awarded a contract by Territory Generation to deliver 81MWh BESS across Australia’s Northern Territory.
April 17, 2026
Akaysha Energy has entered into a deal with Copenhagen Energy to advance “mega-scale” battery energy storage projects in Germany.
April 17, 2026
Synergy has submitted a hybrid renewable energy project to Australia’s EPBC Act, featuring a 500MW battery energy storage system (BESS).
April 16, 2026
Neoen Australia has referred its 3,200MWh Bondo wind-plus-storage project for federal environmental assessment.