Italian oil giant acquires Australian solar-plus-storage project

LinkedIn
Twitter
Reddit
Facebook
Email

Eni Australia, a subsidiary of Italian oil and gas firm Eni, which has been active in Australia since 2000, has acquired a 33.7MW construction-ready solar-plus-storage project in the Northern Territory of Australia, from Katherine Solar, a joint venture between Australia’s Epuron and UK-based firm Island Green Power.

Once completed, the project near Katherine will be the largest PV farm in the Northern Territory and will include a battery storage system with a capacity of 5.7MVA/2.9MWh. A cloud coverage predicting technology will also be installed.

Construction is expected to start in the next few weeks, with an expected commercial operation date in Q4 2019. Epuron will help to manage the PV farm once it is operational.

This initiative marks Eni’s entry in the Australian renewables market. Eni Australia is already the operator and owner of the Blacktip Gas Project and has a non-operated interest in the Bayu-Undan gas and condensate field and in the associated Darwin LNG plant.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The hybrid project will contribute to the Northern Territory’s government goal to procure 50% of its energy from renewable sources by 2030.

Recently, a new 4MW / 8MWh energy storage project was also announced in an area of Queensland, which may also be soon getting a battery ‘Gigafactory’ before long.

Read Next

November 4, 2026
Australia has finished trialling grid-forming battery storage for system security services and needs contracts signed within two years.
Premium
November 3, 2026
ESN Premium speaks with Zane Zhou of CATL Australia and New Zealand, about TENER+, sodium-ion demand, the Collie BESS and more.
November 3, 2026
Revera Energy has doubled its holdco credit facility from US$150 million to US$300 million to fund its BESS pipeline in the UK and Australia.
November 2, 2026
Two Australian battery storage projects in Queensland and Victoria have entered federal environmental review, with AGL Energy and developer ACEnergy each submitting referrals under the same national process.
November 2, 2026
Sungrow will supply both the BESS and the grid-forming power conversion equipment for ENGIE’s Hazelwood BESS expansion in Victoria, Australia.