Ireland to process 373MW of energy storage under new connections procedure

By David Pratt
September 5, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
The new Enduring Connection Policy was brought in to address the rise of solar projects aiming to connect but often facing lengthy delays in receiving offers.

Over 370MW of energy storage projects, along with 1.25GW of solar, have been successfully moved into the ‘first batch’ of projects to be processed under a new connections procedure, brought in to tackle the surging levels of smaller projects aiming to connect.

The Enduring Connection Policy (ECP) was confirmed by Ireland’s regulator, the Commission for Regulation of Utilities (CRU) in March as the new connections processing framework. The existing ‘last gate’ method, which placed projects in a queue, was deemed to be ‘no longer fit for purpose’ following a surge in small-scale solar projects that were often left with lengthy delays to connection.

The new ECP-1 system has been designed to reflect system needs when issuing connection offers for new generation and storage capacity. The first batch of projects has been unveiled by transmission system operator Eirgrid and the electric utility/distribution company ESB Networks, splitting the accepted projects across a series of new categories.

The system operators (SOs) received 2.1GW of applications for those seeking to be prioritised under the country’s DS3 programme, which aims to balance the Irish grid system while higher levels of renewable generation are connected.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

These were assessed on the basis of planning permission to ensure that CRU’s threshold of 400MW was not breached, resulting in 371MW of battery storage projects – including ‘hydrids’ – being accepted into the DS3 band. These will now be processed for connections, with the SOs expected to prioritise ‘shovel ready’ projects that can be rolled out at pace

It is intended these will be used to accommodate rising levels of renewable generation in Ireland, with well over a gigawatt of solar also included in the first batch of the new connections process.

For more detail on the solar projects included in ECP-1, visit PV Tech.

Read Next

December 4, 2025
PJM has awarded 23 battery energy storage system (BESS) resources, totalling 2.2GW, with interconnection agreements (IAs) in its first transition cycle (TC1) of the reformed interconnection process.
December 4, 2025
Zenith secures 25-year PPA with Northern Star for 532MW hybrid project featuring a 138MW/300MWh BESS at Kalgoorlie gold mine in Australia.
December 3, 2025
Stanwell bags rights to Quinbrook’s 6.24GWh Gladstone Energy Hub, combining 780MW battery energy storage with gas generation in Queensland.
December 2, 2025
The Puerto Rico Energy Bureau (PREB) has issued a resolution and order requiring the Puerto Rico Electric Power Authority (PREPA) to complete the Accelerated Battery Energy Storage Addition Programme (ASAP).
December 1, 2025
Fortescue has completed delivery of its first large-scale battery storage system (BESS) to the North Star Junction site in Western Australia.