India plans 14MW of solar with 42MWh of battery storage in Ladakh

February 5, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
Ladakh is a high altitude region in the far north of India. Credit: Tom Kenning

India’s Ministry of New and Renewable Energy (MNRE) is planning two hybrid projects with a combined total of 14MW solar PV and 42MWh of battery energy storage in Leh and Kargil, in the state of Jammu and Kashmir.

The plan comes just a few weeks after Solar Energy Corporation of India (SECI) released a highly ambitious tender for 7.5GW of solar also in the remote and high altitude desert region of Ladakh in the far north of India. The viability of this venture has been questioned by engineers and a pre-bid meeting is to be held on 18 February in New Delhi.

However, the new solar-plus-storage projects, located in different parts of the Ladakh region, will include far smaller project sizes with 7MW of solar and 21MWh of storage each. Ladakh Renewable Energy Development Agency (LREDA) and Kargil Renewable Energy Development Agency (KREDA) will facilitate securing the required land area for each project.

SECI will oversee the scheme and act as project management consultant.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project will have a fixed tariff of INR2/kWh (US$0.028) alongside viability gap funding (VGF) which is a subsidy provided by the government to a maximum of INR1.82 billion (US$25.4 million) for each project in this case. The VGF will be dispersed in two tranches will the final 50% offered on successful commissioning.

SECI will issue a tender and award the projects via competitive bidding. Projects are to be commissioned within 18 months of being awarded and successful bidders will also be responsible for O&M services on the plants.

In other news, SECI is also planning to develop its own renewable energy projects at the Indian archipelago of Lakshadweep, with an eye on coupling the projects with battery energy storage.

Read Next

March 5, 2026
Developer Avantus has closed a financing package of over US$300 million for the 100MWac/130MWdc solar, 400MWh BESS Kitt Solar and Energy Storage Project in Pinal County, Arizona, US.
March 5, 2026
From Texas, US, Bimergen Energy has acquired eight BESS projects totalling 79.2MW. Meanwhile, Habitat Energy announced its first US co-located solar-plus-storage partnership with Birch Creek.
March 3, 2026
3.6GWh of solar-plus-storage developments have progressed in Australia this week, with Edify Energy partnering with DT Infrastructure and Flow Power acquiring a 60MW project.
March 3, 2026
Oregon-based utility company Portland General Electric has finalised agreements for more than 1,000MW of new renewable energy and BESS projects.
February 25, 2026
Experts at the ongoing Energy Storage Summit 2026 have cautioned against treating co-located storage as a “silver bullet” to prop up commercially underperforming solar assets.