India plans 14MW of solar with 42MWh of battery storage in Ladakh

LinkedIn
Twitter
Reddit
Facebook
Email
Ladakh is a high altitude region in the far north of India. Credit: Tom Kenning

India’s Ministry of New and Renewable Energy (MNRE) is planning two hybrid projects with a combined total of 14MW solar PV and 42MWh of battery energy storage in Leh and Kargil, in the state of Jammu and Kashmir.

The plan comes just a few weeks after Solar Energy Corporation of India (SECI) released a highly ambitious tender for 7.5GW of solar also in the remote and high altitude desert region of Ladakh in the far north of India. The viability of this venture has been questioned by engineers and a pre-bid meeting is to be held on 18 February in New Delhi.

However, the new solar-plus-storage projects, located in different parts of the Ladakh region, will include far smaller project sizes with 7MW of solar and 21MWh of storage each. Ladakh Renewable Energy Development Agency (LREDA) and Kargil Renewable Energy Development Agency (KREDA) will facilitate securing the required land area for each project.

SECI will oversee the scheme and act as project management consultant.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project will have a fixed tariff of INR2/kWh (US$0.028) alongside viability gap funding (VGF) which is a subsidy provided by the government to a maximum of INR1.82 billion (US$25.4 million) for each project in this case. The VGF will be dispersed in two tranches will the final 50% offered on successful commissioning.

SECI will issue a tender and award the projects via competitive bidding. Projects are to be commissioned within 18 months of being awarded and successful bidders will also be responsible for O&M services on the plants.

In other news, SECI is also planning to develop its own renewable energy projects at the Indian archipelago of Lakshadweep, with an eye on coupling the projects with battery energy storage.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 13, 2026
Independent power producer (IPP) Clearway Energy has added 210MW of energy storage capacity to its Honeycomb Energy Centre fleet in Southern Utah, US.
October 12, 2026
Distributed energy resource (DER) platform Voltus has raised US$225 million in an oversubscribed Series D financing round and is looking to expand in the US and Canada.
October 6, 2026
Japanese trading company Sumitomo Corporation has invested in a utility-scale renewable energy park combining solar PV, wind and energy storage in India.
October 5, 2026
Join us for In Case You Missed It (ICYMI), our weekly recap of thought-provoking and potentially game-changing news.
October 5, 2026
Debmalya Sen, president of the India Energy Storage Alliance (IESA), on a dynamic market landscape of tenders, tariffs and the race to build a domestic battery storage ecosystem.