Cook Islands latest Pacific territory to use batteries and solar to replace diesel

June 7, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
Rarotonga, capital of the Cook Islands, where the 5.6MWh project will be located.

The Cook Islands in the Pacific will host a 5.6MWh lithium-ion battery energy storage system for the integration of renewables, in a project funded by the Asian Development Bank, European Union and Global Environmental Fund.

The Cook Islands have, in its government’s own words, a “precarious reliance” on importing diesel to generate electricity. As a Pacific Island nation they are also in the frontline of climate change, with a target and plan in place to eliminate emissions and hit full reliance on renewables by 2020.

The latest project, expected to cost around NZ$4.3 million (US$3.09 million), is considered an important part of that Renewable Energy Sector Project, and is meant to provide the utility of the territory’s biggest island and capital, Rarotonga, with increased flexibility for the integration of renewables on its grid.

Australia headquartered developer MPower has been awarded the contract by the Cook Islands’ government to build the plant, which will be connected to a grid-connected 1MW solar PV plant, Te Mana Ra Solar PV. The company said it will be its biggest battery project to date and is thought to be larger than any single installation so far in its home country. MPower said it would rely on expertise in working on the Pacific Islands it had gained through developing 5MW of PV in Samoa.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“We’re pleased to be able to deliver a new era energy to the Cook Islands, employing the latest technologies and building on the renewables program that is well underway,” Nathan Wise, CEO of MPower’s parent company, Tag Pacific Limited, said.

When operational, the plant will be operated and looked after by local workers, which was part of the conditions through which the contract was awarded. The system needs to be able to withstand high temperatures and humidity and will be “physically and operationally modular”, MPower said, implying that it can be scaled up further or other adjustments made in future.

The project is “tentatively” scheduled for completion in the first half of next year. After the design and build phase, MPower will bring in local contractors to work on the project.

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

October 16, 2025
Fluence has announced a solar-plus-storage project in Arizona, while Greenflash Infrastructure adds to its Texas BESS portfolio.
October 16, 2025
Octopus Australia has acquired the Coleambally battery energy storage system (BESS), a 100MW/400MWh standalone project in development located in southern New South Wales.
October 15, 2025
A flurry of grid-scale BESS project progress totalling more than a combined 1.5GWh in the past week, from Renalfa in Bulgaria, Engie in Romania, Nala Renewables in Finland and Metlen in Greece.
October 15, 2025
Takeaways from the first day of Energy Storage Summit Latin America 2025, including the Chilean and Argentinian markets.
October 15, 2025
Publicly-owned energy company CleanCo Queensland’s 250MW/500MWh Swanbank battery energy storage system (BESS) has officially registered with AEMO and commenced its testing and commissioning phase.

Most Popular

Email Newsletter