Battery storage called into action as UK suffers country-wide power cuts

By Liam Stoker
LinkedIn
Twitter
Reddit
Facebook
Email
Image: Anesco.

Battery storage assets were called into action last week after the UK suffered country-wide power outages following a transmission system stress event. 

Last Friday evening (9 August 2019), two large generators were disconnected from the UK’s power system almost simultaneously, effectively taking 2GW worth of electricity generation within minutes of each other. 

That collapse in generation sent the country’s transmission grid frequency to dip to 48.9Hz, far outside the frequency required for it to safely operate. 

National Grid, the country’s electricity system operator (ESO), called on reserve and flexible generation capacity to respond, with many operators dispatching battery storage capacity to meet National Grid ESO’s calls. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Mike Ryan, asset management director at battery storage developer Anesco, said the incident was made all the more interesting by the role battery storage ended up playing throughout the event’s 40-minute duration. 

As the level of flexible reserve capacity was not sufficient to meet the 2GW shortfall, National Grid ESO had little option but to begin cutting off consumers and other sources of demand to protect grid infrastructure. While this resulted in widespread disruption for consumers up and down the UK, it also had another consequence on power demand. 

“When National Grid cut off the power, the frequency bounced back very quickly, sending the system the other way and meaning our battery sites were then called on to balance the grid by taking power out,” Ryan said. 

“There has never been a clearer example of the vital role of storage for the grid. As more and more renewable generators come online and we drive towards ‘net zero’, such assets need to be effectively utilised and proper frameworks put in place to work with operators.”

However, National Grid ESO has also come in for criticism, with some industry stakeholders remarking the blackout evidences the need for the system operator to contract far great quantities of flexible storage capacity.

Mark Simon, chief executive at battery storage owner and operator Eelpower, said:  “The power cut… shows how the volatility of wind power generation, when it is the dominant provider of electricity, can introduce significant systemic risks.   

“These risks will only be balanced by the introduction of high-speed, grid-connected electricity storage distributed across the country, and delivered at scale.  It’s vital that the National Grid, local grid companies and battery storage operators work together to ensure that events like this afternoon’s power cut do not become commonplace… It demonstrates with great clarity the urgent need for electricity storage at scale on the UK’s grid. “  

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

June 19, 2026
Developer BLT Energy has received development approval for the 800MW/4,800MWh Red Gully BESS in Western Australia.
June 19, 2026
Energy storage developer Eku Energy has submitted two BESS, each sized at 300MW and 1,200MWh, for assessment under Australia’s EPBC Act.
June 18, 2026
Energy storage developer-operator Aypa Power and utility Salt River Project (SRP) have brought the 250MW/1,000MWh Pediment energy storage project online in Mesa, Arizona.
June 18, 2026
Fire and Rescue NSW (FRNSW) in Australia has set out its requirements for lithium-ion battery storage rooms and diesel generator structures in data centres.
Premium
June 15, 2026
ESN Premium speaks with ASL on the latest FERM tender results in South Australia and why batteries excelled.