Batteries to provide reactive power services to UK electric grid

March 6, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Gresham House utility-scale battery energy storage project in Britain. Image: Gresham House.

Batteries are to be used for reactive power services for the UK grid as part of a ‘world-first’ project to create a new reactive power market for distributed energy resources (DERs).

UK battery storage company Zenobe Energy is putting 10MW of battery storage, located at its King Barn facility in Sussex, south England, into the Power Potential Project, run by electric system operator National Grid ESO.

Reactive power is an increasingly important part of the UK grid, maintaining voltage levels to allow more energy to be transported down existing infrastructure. It therefore increases the capacity of the transmission system without having to upgrade infrastructure.

As more intermittent renewables have come onto the grid, the need to finely balance the voltage has led National Grid ESO to explore a number of reactive power solutions. Zenobe’s battery storage will provider those services to National Grid ESO via the lines of distribution network operator (DNO), UK Power Networks (UKPN).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The Power Potential Project, spearheaded by National Grid ESO and UKPN, is looking for create a new reactive power market for distributed energy resources (DERs) in the South East. It could save consumers over £400m (US$518.80 million) by 2050, as well as generating up to an additional 4GW.

Zenobe’s batteries will be able to absorb and generate reactive power to alleviate capacity challenges as distributed energy generation in the region continues to grow.

Live testing of the battery system will now take place with UK Power Networks throughout March, following successful trials in a lab last year. Last year, a UK solar farm operated by Lightsource BP helped provide reactive power as part of the project.

This story first appeared in its original form on Current±.

Oversubscribed share placing for UK listed fund raises over US$40m

London Stock Exchange-listed energy storage investment vehicle Gresham House Energy Storage Fund has raised £31.2 million (US$40.47 million) in an oversubscribed share placing, with funds earmarked for a potential acquisition.

The fund raised the money in gross proceeds through the issue of 30 million shares at a Placing Price of 104 pence per share. The proceeds of the placing are to be used to complete the potential acquisition of a “significant operational project” that has the potential for expansion over 50MW, Gresham House said.

It is to fund the 10MW extension of the Glassenbury project, acquired in December 2019, with the balance to provide increased working capital. Gresham House has made a number of UK battery storage acquisitions lately, including the 49MW Red Scar battery and a 10MW battery in Kent.

Ben Guest, manager of Gresham House Energy Storage Fund, said its discussions with investors suggest “growing confidence in our plans, and deepening understanding of the importance of battery storage in facilitating a reliable and cost-effective energy transition”.

“These are undoubtedly factors that investors take into consideration in deciding which opportunities to back in the renewable infrastructure sector,” Guest added, confirming the funding in this round came from both existing investors and new names.

Gresham House’s portfolio has a current capacity of 174MW, having raised £238 million in the 15 months since its London Stock Exchange IPO.

This story by Alice Grundy.

This story first appeared in its original form on Solar Power Portal.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

April 24, 2026
The rapid digitisation of energy infrastructure represents a big challenge, says Michael Hudson, cybersecurity strategy director at Sungrow North America.
Premium
April 24, 2026
How can energy storage capitalise on energy price volatility in European markets, and how do investors need to think about future opportunities and challenges? An expert panel at the Energy Storage Summit 2026 in London in February dived into the topic.
Premium
April 24, 2026
How much long-duration energy storage (LDES) does the UK system need, is the government’s cap-and-floor the right way to procure it, and what does the long-term picture look like?
April 23, 2026
Two US battery recycling companies, Redwood Materials, and Ascend Elements, are in less than optimal situations, with Redwood laying off 135 employees, and Ascend filing for Chapter 11 bankruptcy.
April 22, 2026
Bobwhite Energy Storage, an affiliate of independent power producer (IPP) Tenaska has signed a long-term energy storage agreement (ESA) with utility Tennessee Valley Authority (TVA) for a 225MW/900MWh project in East Tennessee, US.