Approvals for two major solar farms in NSW = 430MWh more battery storage in Australia

March 11, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Solar monitoring point put in place at the proposed site of the Wollar Solar Farm. Image: Wollar Solar Development Pty Ltd.

Developers of two significant solar-plus-storage projects in the Australian state of New South Wales have been given the go-ahead, with only minor conditions added to their proposals.

The NSW government’s Independent Planning Commission approved on 9 March 2020 an AU$768 million (US$503 million) solar-plus-storage project on the Northern Tablelands, despite the proposed development initially receiving 67 public objections.

Developer UPC Renewables Australia will now be able to kickstart the 720MW New England Solar Farm, which will be combined with 200MW/400MWh of lithium-ion battery storage and set on 3,362 hectares of agricultural land, 6 kilometres east of Uralla.

The NSW government also moved recently to approve the 290MW Wollar Solar Farm. The project, featuring a proposed 30MW/30MWh battery storage add-on, has been deemed in the public interest.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The AU$431 million (US$282 million) project is being developed by Wollar Solar Development Pty Ltd, a renewable energy firm set up in 2017. The system is located seven kilometres south of Wollar Village and is set to create up to 320 construction jobs. The battery storage facility will also offer dispatchable power to the National Energy Market (NEM), with both projects contributing to NSW’s shift away from fossil fuels.

The NSW Department of Planning, Industry and Environment deemed that Wollar’s impacts on the community and the environment can be appropriately minimised, managed or offset to an acceptable level, subject to certain conditions.

It said the land could be easily returned to agriculture land following decommissioning and it also considered the visual impact of the project on the surrounding residences and road users to be minimal.

To read the full version of this story, visit PV Tech.

Read Next

April 28, 2026
IPP Grenergy has entered into a long-term toll with an ‘investment grade’ international utility for a solar PV co-located BESS of 680MWh in Spain.
April 28, 2026
Sumitomo Electric will supply a vanadium redox flow battery (VRFB) energy storage system to enable grid integration of wind energy in Hokkaido, northern Japan.
April 28, 2026
Australian infrastructure contractor GenusPlus Group has been awarded an AU$110 million (US$78.5 million) engineering, procurement, construction and commissioning contract for the 200MW/800MWh Koolunga battery energy storage system (BESS) in South Australia.
April 28, 2026
ARENA is supporting two First Nations-led microgrid projects in the Northern Territory (NT) with AU$11 million in funding.
April 27, 2026
Update 28 April 2026: Following publication of this story, Hydrostor reached out to clarify some of the conditions detailed below and provided a statement.