Netherlands: Giga Storage claims first time-limited contract for BESS

August 27, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

BESS developer-operator Giga Storage has agreed a time-limited grid usage contract with Netherlands’ TSO TenneT, the first of its kind, the firm claimed.

The firm has concluded the first ever-time limited contract with TenneT, it said, which will give it the right to charge or discharge from the grid for 85% of the day.

The deal has been agreed for Giga’s 300MW/1,200MWh Leopard project in Vlissingen, northern Netherlands, on which construction should start this year, as told to Energy-Storage.news by the firm’s CCO Lars Rupert in June. The time limited contract becomes active on 1 October, 2025, although Giga has previously said Leopard would come online in 2026.

The new contract type was brought in as part of the Landelijk Actieprogramma Netcongestie (National Action Programme for Grid Congestion) reforms, and aims to ease grid congestion in the Netherlands while allowing new projects to be built.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Netherlands Minister of Climate and Green Growth Sophie Hermans commented on the announcement: “We are all working very hard to expand the power grid faster, and we also need to use the grid smarter. Thanks to this new type of contract and good cooperation, it will be possible to make the best use of the space left on the grid outside ‘peak hours’. And moreover, to deploy renewable electricity when there is less sun and wind. I hope this is a breakthrough and other companies that can do so will also consider a flexible contract.’

In return for limiting when the BESS interacts with the grid, Giga Storage’s project will get a 65% discount on transmission tariffs. Energy-Storage.news interviewed research firm Aurora about the new contract recently, with analyst Jesse Hettema saying the economics of it should pencil out, and subsequently boost the grid-scale BESS market (Premium access).

However, the commercial director for Giga Storage’s peer SemperPower, which owns the two largest operational projects in the Netherlands today, was more sceptical about the time-limited contracts when asked about them. The contracts can be used by any large user of electricity, including commercial and industrial (C&I) locations that can flexibilise their power consumption.

The Dutch market appears to have turned a corner in the last year with several large-scale projects announced, alongside Giga’s Leopard, including a 640MWh BESS being developed by SemperPower in partnership with developer Corre Energy and a 1.5GWh one from Lion Storage receiving a construction permit.

Read Next

March 6, 2026
Inverter and BESS firm Sungrow and BESS owner-operator Delta Capacity signed a 1GWh framework supply agreement for European projects at the Energy Storage Summit 2026 in London last week.
Premium
March 5, 2026
In this second part of our interview with Wood Mackenzie energy storage analysts, we look at risk factors and mitigation across the European and US markets.
Premium
March 4, 2026
ESN Premium takes advantage of an opportunity to compare Europe and US energy storage markets with Wood Mackenzie energy storage analysts.
February 27, 2026
US energy storage and battery technology startup Lyten has completed its acquisition of Northvolt’s business operations in Sweden and announced its immediate plans.
February 27, 2026
Iron-sodium battery manufacturer Inlyte Energy and data centre operator NTS Colocation are partnering to deploy 2MW of iron-sodium battery capacity by 2028.