Indian energy storage tender delayed as price caps are too low

September 23, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

Industry members have informed SECI that the cap on viability gap funding is too low for battery costs. Credit: SECI
India’s first major utility-scale tender for solar PV combined with energy storage in the state of Andhra Pradesh has been put on hold due to the cap on tariffs being too low.

Solar Energy Corporation of India (SECI), which announced the tender in August for 10MWh storage to be combined with two 50MW solar plants in the Kadapa Solar Park, set the tariffs at the same level as that of solar.

This includes a benchmark tariff of INR4.43/kWh (US$0.066) combined with viability gap funding (VGF) from the government. However, energy storage industry members have informed SECI that the cap on the VGF is too low.

Gautham Nalamada, executive director and chief executive of Hyderabad-based firm Photon Energy Systems, told Energy Storage News that current VGF levels would only account for 25% of battery costs. Furthermore, the specifications on storage were not clear enough for hopeful developers.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Nalamada said that SECI had believed that only requiring 30 minutes backup for load shifting would be affordable, but the industry has responded by claiming that even this capacity is too expensive at present.

He added: “The tender has now been put on hold and they are redrafting the specifications.”

In July, consultancy firm Bridge to India said that the capacity of SECI’s planned storage procurements in Andhra Pradesh and Karnataka were negligible, but they would act as a kind of acclimatisation process for these technologies in India, so this delay in procurement will not have helped that cause.

Nonetheless, after a recent visit to the UK with an Indian trade delegation, Nalamada said that while he had assumed that storage would take four to five years to blossom in India, it may now take just two or three years. He said that UK utility pricing was not dissimilar to the Indian model and storage was already playing a role in the UK so can do the same in India.

Read Next

January 15, 2026
ASL has launched a consultation on a new Hybrid Generation LTESA product alongside its 2026 NSW Consumer Trustee Investment Priorities.
January 9, 2026
Jointly owned by Masdar and Igneo Infrastructure Partners, independent power producer (IPP) Terra-Gen’s Lockhart CL I and II battery energy storage system (BESS) projects have reached commercial operations in San Bernardino County, California, US.
January 9, 2026
Yanara has appointed Gamuda Australia as the project delivery partner for the early contractor involvement (ECI) phase of the Mortlake Energy Hub in Victoria.
January 6, 2026
It’s our first week back to normal service so here’s a roundup of the past few weeks of BESS action in Europe, with projects moving forward in Romania, Denmark, UK, France, Spain, Albania, Germany and Austria.
January 6, 2026
An energy storage subsidiary of Waaree Energies has raised INR10 billion (US$110.9 million) for a planned manufacturing plant in India.