Indian energy storage tender delayed as price caps are too low

LinkedIn
Twitter
Reddit
Facebook
Email

Industry members have informed SECI that the cap on viability gap funding is too low for battery costs. Credit: SECI
India’s first major utility-scale tender for solar PV combined with energy storage in the state of Andhra Pradesh has been put on hold due to the cap on tariffs being too low.

Solar Energy Corporation of India (SECI), which announced the tender in August for 10MWh storage to be combined with two 50MW solar plants in the Kadapa Solar Park, set the tariffs at the same level as that of solar.

This includes a benchmark tariff of INR4.43/kWh (US$0.066) combined with viability gap funding (VGF) from the government. However, energy storage industry members have informed SECI that the cap on the VGF is too low.

Gautham Nalamada, executive director and chief executive of Hyderabad-based firm Photon Energy Systems, told Energy Storage News that current VGF levels would only account for 25% of battery costs. Furthermore, the specifications on storage were not clear enough for hopeful developers.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Nalamada said that SECI had believed that only requiring 30 minutes backup for load shifting would be affordable, but the industry has responded by claiming that even this capacity is too expensive at present.

He added: “The tender has now been put on hold and they are redrafting the specifications.”

In July, consultancy firm Bridge to India said that the capacity of SECI’s planned storage procurements in Andhra Pradesh and Karnataka were negligible, but they would act as a kind of acclimatisation process for these technologies in India, so this delay in procurement will not have helped that cause.

Nonetheless, after a recent visit to the UK with an Indian trade delegation, Nalamada said that while he had assumed that storage would take four to five years to blossom in India, it may now take just two or three years. He said that UK utility pricing was not dissimilar to the Indian model and storage was already playing a role in the UK so can do the same in India.

31 October 2025
Greater Noida, India

Read Next

August 14, 2025
India’s ambitious drive for renewable energy has accelerated the need for energy storage, but there are many factors to success, writes Charith Konda of the Institute for Energy Economics and Financial Analysis (IEEFA).
August 12, 2025
Fluence expects to hit the lower end of its previously issued revenue guidance for the 2025 financial year due to delays in ramping up at US production sites.
Premium
August 6, 2025
Energy-Storage.news Premium speaks with microgrid solutions provider BoxPower’s Director of Business Development, Fallon Vaughan and Sales and Marketing Coordinator Noa Schachtel, about the company’s microgrid offerings.
August 5, 2025
CATL, the world’s biggest lithium-ion OEM, saw flat ESS revenues in the first half of the year, but the extent to which this can be blamed on the increased US-China tariffs, if at all, is far from clear.
July 30, 2025
Maharashtra State Electricity Distribution Co (MSEDCL) has launched a multi-gigawatt battery storage tender supported by Viability Gap Funding (VGF).

Most Popular

Email Newsletter