Ignitis Group and Olana Energy have progressed BESS projects in Lithuania closer to construction, with the order of equipment and final investment decision (FID) taken, respectively.

The new double-header of news comes a few weeks after the country’s Ministry of Energy said that its EU-backed energy storage capex support scheme could support as much as 4,000MWh of projects. The need for the technology is growing as more renewable power capacity come online, while the Baltic region’s decoupling from Russia’s BRELL system and synchronisation with mainland Europe created an additional requirement.

Ignitis orders BESS for three projects

Utility and power generation firm Ignitis Group has ordered 291MW/582MWh of battery energy storage system (BESS) equipment from the system integrator arm of power solutions firm Rolls-Royce for three projects in Lithuania.

Rolls-Royce Power Systems will supply its mtu EnergyPack solution for the order, its largest ever, the conglomerate said today (16 September).

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The BESS will be deployed alongside other clean energy plants, the Kelmė and Mažeikiai wind farms and the Kruonis pumped storage power plant, and are expected to be online in 2027.

Darius Maikštėnas, CEO of Ignitis Group, said: “Power generation from renewables is growing in Lithuania, which makes battery energy storage systems an important guarantee of reliability. They make the network more flexible, enable efficient use of green energy and help maintain stability even through heavy fluctuations. Battery energy storage systems are a key component of green transition as they will help integrate more green capacities, balance the fluctuations in power prices as well as reduce them.”

Ignitis made a final investment decision (FID) on the three projects in July this year.

Olana Energy buys and takes FID on 70MW/140MWh project

In concurrent news, Finland-headquartered BESS developer-operator Olana Energy has taken FID on a 2-hour project in Šalčininkai, Lithuania. It is the company’s first project with FID outside of Finland.

The 70MW/140MWh BESS was acquired from developer Aura Power and will be among the largest in the country when it comes online in Q4 2026, Olana said. The project has been designed with a power and capacity oversizing strategy, it added.

Olana was formerly known as Biosolar, but its increasing focus on storage led it to rebrand last year. It has 25MW of operational projects in Finland and a 1GW pipeline in Finland and elsewhere.

2 December 2025
NH Collection Vittorio Veneto, Rome, Italy
Across two packed days, the Summit focused on three core themes: revenue & trading, the lifecycle of the battery, and optimisation tools. Attendees explored innovative strategies for enhancing asset performance and longevity, with a spotlight on key markets like Germany, Italy, and the UK. Stay tuned for details on the 2025 edition of the Battery Asset Management Summit Europe, where we’ll continue to chart the path forward for energy storage asset management.
24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

October 6, 2025
Asset manager AIP Management has bought a 49% stake in a 2.4GWh UK portfolio from global BESS investment platform BW ESS for a deal in excess of £650 million (US$873 million).
October 3, 2025
BESS provider Sungrow and power firm Engie have connected the first phase of a 400MW/800MWh project, one of the largest in Europe, to the grid in Belgium.
Premium
October 2, 2025
Investor-owned utility (IOU) Southwestern Public Service Company (SPS) is seeking approval from the New Mexico Public Regulation Commission (NMPRC) to construct a new eight-project portfolio of self-build energy assets.
October 2, 2025
The TSO of Italy has completed its first MACSE auctions for energy storage, procuring 10GWh of capacity at what the NHOA CEO called ‘exceptionally competitive prices’.
October 1, 2025
Power firm VPI has signed a 700MW pipeline BESS joint venture in Germany with developer Noveria Energy, while system integrator ADS-TEC has revealed a 1GW/2GWh project.

Most Popular

Email Newsletter