
ASX-listed Frontier Energy has started construction on Stage 1 of its Waroona Renewable Energy Project in Western Australia (WA), which pairs solar PV with a battery energy storage system (BESS).
Stage 1 comprises a 132MW solar PV plant and an 81.5MW/570.5MWh BESS that Frontier said will provide about 7 hours of storage. The site is about 8km south-west of Waroona and 120km south of Perth, close to existing high-voltage transmission at the Landwehr Terminal.
WA energy and decarbonisation minister Amber-Jade Sanderson and federal assistant minister for climate change and energy Josh Wilson joined Frontier representatives for the sod turning on Friday (13 November). First generation is scheduled for 2028.
Frontier said Stage 1 is expected to be the largest solar-plus-storage hybrid facility connected to the South West Interconnected System (SWIS), WA’s main grid, which sits outside the National Electricity Market (NEM). Construction is expected to employ up to 200 people at its peak.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
“Breaking ground at Waroona is a major milestone for Frontier and marks the point where years of development work move into construction,” said Adam Kiley, CEO of Frontier Energy.
The groundbreaking follows Frontier signing an AU$280 million (US$189 million) syndicated debt facility for Stage 1 on 2 November, led by Natixis Corporate & Investment Banking and Sumitomo Mitsui Banking Corporation (SMBC), as our sister site PV Tech reported when Frontier signed the debt facility for the Waroona project.
Frontier said the debt, together with an AU$110 million equity placement completed in July, is expected to fully fund Stage 1 through to first generation. Financial close was expected in November, subject to conditions including a Capacity Investment Scheme (CIS) agreement with the federal government.
“With more than AU$310 million being invested in Waroona, this project is a strong vote of confidence in WA’s clean energy future,” said Wilson.
In September, Frontier contracted Trina Storage, the energy storage business of Trina Solar, to supply the 562MWh BESS, as Energy-Storage.news reported when Trina Storage was selected for the Waroona solar-plus-storage project. The deal includes a 20-year warranty and a long-term services agreement.
Western Australian contractor Monford Group holds the fixed-price engineering, procurement and construction (EPC) contract. Connection agreements with Western Power, the state-owned network operator, allow exports of up to 99MW and imports of up to 95MW to charge the BESS.
The project was paused in October 2024 after missing out on Reserve Capacity Credits from the Australian Energy Market Operator (AEMO). Frontier has since extended the storage duration to 6.9 hours to meet a 6-hour minimum under WA’s reserve capacity rules.
Kiley said the project combines large-scale solar PV with long-duration storage so it “can store low-cost energy during the day and deliver it when Western Australia needs it most”.
CIS backing and Western Australia’s storage pipeline
The Stage 1 BESS is backed by Tender 6 of the CIS, the federal scheme that underwrites revenue for new renewable energy and storage capacity. Frontier has said the award gives the project downside revenue protection until 2042.
Waroona was one of three BESS selected under Tender 6 in May, listed at 82MW/565MWh, as WA was awarded 1.9GW of renewables and 3.7GWh of battery storage under CIS Tenders 5 and 6. All projects are due to be commissioned by 2030.
The other two Tender 6 winners are Neoen’s 200MW/1,600MWh Yathroo Battery and Enpowered and Plenary Group’s 200MW/1,518MWh Collie Battery and Solar Hybrid Project. Tender 6 contracted 3,683MWh in total, more than 50% above its 2.4GWh target.
“We know that wind and solar, backed by storage and gas, is the cheapest and most reliable energy mix for the future,” said Sanderson.
Tender 5, for generation, also included a solar-plus-storage hybrid: Trina Solar’s 350MW Killawarra Hybrid Project in Kadathinni, with 2,100MWh of battery storage.
In the NEM, Neoen has started building a 215MW/963MWh BESS sharing the grid connection of its Culcairn solar PV plant in New South Wales, as Energy-Storage.news reported when Neoen, Frontier Energy and Lightyears secured financing for solar-plus-storage in Australia and New Zealand.
Frontier plans to expand Waroona to more than 1GW of generation capacity and said planning for Stage 2 is already advanced. PV Tech reported that Stage 2, of about 120MW of solar PV and 80MW of storage, has development approval.
Never miss an Australian energy storage story. Sign up for our Australia newsletter and get the latest project announcements, policy updates and market analysis delivered directly to you.