Fire at Moss Landing plant in California

January 17, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

A fire broke out yesterday (16 January) at the Moss Landing facility which houses what was once the world’s largest BESS, owned by Vistra Energy, in California, US.

A statement from utility Vistra Energy late yesterday, cited widely by local outlets, said that a fire had broken out at the Moss Landing Power Plant site which houses the 750MW/3,000MWh Moss Landing Energy Storage Facility battery energy storage system (BESS), alongside a natural gas plant also owned by Vistra.

The Monterey County Sheriff’s office also confirmed a fire at the Moss Landing Power Plant, and local highways were cleared and residential areas evacuated.

Media cited a Vistra spokesperson saying that emergency responders were called after a fire was detected at the 300MW Phase I portion of the BESS project, which was built in three phases reaching full capacity in August 2023.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The incident is not a ‘current incident’ on the website of the California Department of Forestry and Fire Protection (CAL FIRE) but the evacuation order around the site still appears to be in place.

The County of Monterey meanwhile still has a current emergency alert for the site up, but doesn’t list it as a current emergency incident: “Due to an ongoing large fire in Moss Landing, Monterey County Health officials are advising residents to stay indoors, keep windows and doors closed, limit outdoor exposure, and turn off ventilation systems. Monitor local news and social media for additional updates. Further information will be provided as the situation changes.”

An adjoining site houses the separate 182.5MW/730MWh Elkhorn Battery BESS project, owned by utility and transmission and generation operator PG&E.

It is not the first time the Moss Landing BESS plant has suffered from fire safety issues. Both of the first two phases, totalling 400MW/1,600MWh, were taken offline in early 2022 after overheating incidents – though that was found to be due to a faulty sprinkler system responding to smoke from an air handling unit.

After this article was published, Energy-Storage.news received statements from both Vistra Energy and PG&E, which read as follows:

Vistra Energy

There is an ongoing fire at our Moss Landing Power Plant site. Our top priority is the safety of the community and our personnel, and Vistra deeply appreciates the continued assistance of our local emergency responders.

Thursday afternoon, Vistra personnel called for assistance from the North Monterey County Fire District after a fire was detected in the 300-MW Phase I energy storage facility at the Moss Landing Power Plant site. All site personnel were safely evacuated. 

The cause of the fire has not yet been determined, but an investigation will begin once the fire is extinguished.

PG&E

The safety of our customers, coworkers, contractors and the communities we serve is PG&E’s top priority.

Around 3:15 P.M. Thursday (1/16) PG&E became aware of a fire at the Moss Landing Power Plant in Monterey County.

The Moss Landing power plant and the battery energy storage system onsite at the power plant are owned and operated by Vistra.

This is NOT a PG&E incident but we have engaged with local first responders and Vistra to assist as needed.

Please reach out to Vistra or to the North County Fire Department for more information.

Read Next

Premium
December 8, 2025
Supervisors in Maricopa County, Arizona, have approved a 100MW/400MWh battery storage project from National Renewable Solutions (NRS).
December 3, 2025
Energy-Storage.news proudly presents our sponsored webinar with Trina Storage, ‘Powering Certainty: Bankable Energy Storage, with Elementa 2 Pro’.
November 28, 2025
Battery storage products from prominent international providers Sungrow, Wärtsilä and Chint Power have undergone recent fire safety tests.
November 25, 2025
Texas-based IPP Vistra Energy has informed the California Energy Commission (CEC) that it will not be advancing its 600MW Morro Bay battery energy storage system (BESS).
Premium
November 21, 2025
The Community Development and Infrastructure Department at Santa Cruz County has become the latest California jurisdiction to publish a draft zoning ordinance regulating the deployment of battery energy storage systems.