Construction imminent on major solar-wind-storage hybrid plant in Queensland

LinkedIn
Twitter
Reddit
Facebook
Email
The park includes 43MW of wind, 15MW of solar on single-axis trackers, and two lithium-ion batteries. Credit: Windlab

Construction on Australia’s first utility-scale wind, solar and energy storage hybrid project to be connected to the national grid is about to start near Hughenden in northwest Queensland.

Australian developer Windlab put out a similar release in October, but construction on the roughly 60MW plant is now due to start today. The project is owned by Windlab and its equity partner Eurus Energy Holding Corporation of Japan.

The innovative AU$160 million Kennedy Park Energy will take around 12 months to construct and is expected to be completed and start feeding clean energy into the network by late 2018, according to Windlab’s executive chairman and chief executive Roger Price.

He added: “This is an industry first that will produce and feed clean renewable energy into the grid with much greater consistency and reliability from a combination of solar, wind and battery storage. It’s also an important and valuable demonstration of how renewable energy can be used to cost effectively meet most network demand for power – day and night. We believe that this style of hybrid configuration will be increasingly used, particularly in remote locations and emerging markets, as the world transitions to a clean energy future. We are excited about the opportunities that the expertise gained from this pioneering project will present as we seek to replicate it across selected locations in Australia and Southern Africa.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The park includes 43MW of wind, 15MW of solar on single-axis trackers, and two lithium-ion batteries. This includes 56,000 solar panels and twelve Vestas V136, 3.6MW wind turbines.

Kennedy Energy Park secured finance from the Clean Energy Finance Corporation (CEFC) and the Australian Renewable Energy Agency (ARENA), as part of ARENA’s Advancing Renewables Programme.

Utility CS Energy will purchase the energy from Kennedy Energy Park under a 10-year power purchase agreement.

In a statement, Windlab said: “Queensland’s typical daily electricity demand increases during late afternoon and evening and is well matched to the timing to the state’s wind energy profiles. This means Queensland wind farms will produce most of their electricity at these times, which coincide with high network demand. Combining wind with the large amounts of solar generation expected to be added to the Queensland grid, will allow a higher penetration of renewable energy at lower costs while reducing the need for storage and other peaking capacity across the network.”

The next stage of the project named ‘Big Kennedy’ is set to provide up to 1,200MW of wind energy as well.

Read Next

May 14, 2026
Developer Akaysha Energy has received federal environmental clearance for its 400MW/1,600MWh Glenrowan battery energy storage system (BESS) in Victoria, with the project deemed “not a controlled action” under Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act.
May 14, 2026
Australia has clawed back AU$1.3 billion (US$940 million) in uncommitted clean energy manufacturing funding, with the Solar Sunshot Program and Battery Breakthrough Initiative among the programmes hit by budget cuts announced this week.
May 13, 2026
In this US news roundup, battery energy storage system (BESS) project updates from Spearmint Energy in Texas, Polaris Renewable Energy in Puerto Rico, and Clearway Energy Group in Utah.
May 13, 2026
Utility-scale battery storage systems in Western Australia supplied 37.2% of peak demand on 9 May, marking one of the highest battery storage penetration levels recorded in an isolated grid globally.
May 12, 2026
Energy storage owner-operator BW ESS has submitted a 700MW battery energy storage system (BESS) to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act for environmental assessment.