CleanCo Queensland’s 500MWh Tesla Megapack BESS at former coal site enters commissioning in Australia

LinkedIn
Twitter
Reddit
Facebook
Email

Publicly-owned energy company CleanCo Queensland’s 250MW/500MWh Swanbank battery energy storage system (BESS) has officially registered with AEMO and commenced its testing and commissioning phase.

The battery storage system is located at the former Swanbank coal power station site, approximately 45km south-west of Brisbane in Ipswich, Queensland. It will be sited at the Swanbank B site, which was commissioned in 1971 with four 120MW steam turbines powered by coal and decommissioned in 2012.

The project repurposes retired coal-fired generation infrastructure. The broader site will be developed into a clean energy hub, with potential future additions including wind, solar, hydrogen production and additional energy storage capacity.

Tesla supplied its Megapack solution for the Swanbank project, while Yurika provided infrastructure and installation services. The AU$330 million (US$214 million) development received funding from the Queensland Renewable Energy and Hydrogen Jobs Fund.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Reusing existing transmission infrastructure at the legacy coal site enables faster deployment and cost-effective integration of the new energy storage asset into the National Electricity Market (NEM).

The system connects to the electricity grid via a new 275kV substation, utilising the established transmission connections that previously served the coal-fired power station.

Commissioning activities are expected to progress through late 2025, with commercial operation targeted for early 2026.

The Swanbank battery joins a growing pipeline of large-scale energy storage projects across Queensland as the state transitions toward higher renewable energy penetration. The project’s commissioning follows the recent registration of Australia’s first 8-hour long-duration energy storage system with AEMO, demonstrating battery energy storage deployments’ increasing scale and duration capabilities.

Queensland’s energy storage sector has benefited from recent policy support, with over 15GWh of energy storage capacity successful in Australia’s Capacity Investment Scheme tender, providing revenue certainty for large-scale battery projects across the NEM.

480MWh Mornington BESS advances through commissioning phase

Meanwhile, engineering, procurement, and construction (EPC) provider ACLE Services has completed construction of the 240MW/480MWh Mornington BESS on Victoria’s Mornington Peninsula and commenced commissioning activities.

The Mornington project, developed by Valent Energy, features a 2-hour duration configuration with 240MW of power capacity and 480MWh of energy storage. The system utilises CATL battery technology and Power Electronics inverters, with ACLE Services serving as the facility’s EPBC contractor.

Valent Energy completed a 12-month construction period for the project, which connects to AusNet Services’ Tyabb Terminal Station. The developer has positioned the Mornington BESS as part of a broader portfolio totalling over 1.6GW of battery energy storage projects across Australia, with backing from Gaw Capital Partners and BW ESS.

The commissioning phase extensively tests all system components, including battery modules, inverters, control systems and grid integration protocols. These final commissioning activities will validate the system’s performance capabilities before commercial operation begins.

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

October 14, 2025
IPP Eolian has closed a US$463 million financing package to support the continued construction of Padua 2 and Padua 3, two battery energy storage systems (BESS) totalling 350MW/1.7GWh in Bexar County, Texas.
October 14, 2025
Developer Epic Energy has commenced commercial operations at its 100MW/200MWh Mannum battery energy storage system (BESS) in South Australia.
Premium
October 14, 2025
Battery storage equipped with optimisation platforms not specifically designed for Australia’s NEM missed revenue opportunities during the 10 October price spike, according to Sahand Karimi, co-founder and CEO of OptiGrid.
October 13, 2025
Residential energy storage startup Base Power has raised US$1 billion in Series C financing from venture capital fund Addition.
Premium
October 13, 2025
A total of 49.4GW/136.5GWh of grid-scale BESS came online in the first nine months of the year, up 36% compared to the same period in 2024.

Most Popular

Email Newsletter