Australia’s Queensland Hydro pushes on with 48GWh PHES despite government scrutiny

LinkedIn
Twitter
Reddit
Facebook
Email

State-owned pumped hydro energy storage (PHES) developer Queensland Hydro is set to progress the development of its 2GW/48GWh Borumba site despite state government concerns about its viability in Australia.

Revealed last week, the developer has confirmed it is inviting comments on its draft preliminary documentation, which the Commonwealth government is assessing as part of the approval process for the Borumba project’s proposed exploratory works. 

The draft documentation outlines the current environmental state, proposed exploratory activities, potential impacts, and Queensland Hydro’s strategies to avoid, minimise, or offset those impacts.

Exploratory works include surface geotechnical investigations like drilling boreholes, test-pitting, tunnelling, and necessary support to ensure workforce access and accommodate.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Local communities, business owners, and environmental groups near the Borumba project, as well as the general public, are invited to comment on the draft preliminary documentation. The comment period is currently open and will close at midday on 10 March 2025.

Natasha Patterson, Queensland Hydro’s executive general manager of communities and environment, noted the importance of community input, highlighting that the project is “ultimately better off” with input from neighbours and local communities.

“The draft documentation steps through the proposed exploratory works activities in detail and explains our approach to avoiding, minimising or offsetting any impacts. Our teams are working hard to ensure we minimise our impact on natural and cultural values and provide lasting, positive impacts for both the environment and local communities,” Patterson added.

State government scrutiny of the Borumba PHES site

When the right-wing Liberal National Party (LNP) of Queensland, led by premier David Crisafulli, won the state election in October 2024, pumped hydro soon became a target by the incoming government. This led to the cancellation of the world’s largest PHES site, the 5GW/120GWh Pioneer-Burdekin Pumped Hydro Project in November.

The government cited that the project was “not financially viable, not environmentally appropriate, and the community was never consulted”. A report found that the AU$36 billion (US$22 billion) project would have led to unnecessary additional costs for Queensland residents, with each household spending AU$15,653.

Following this, the government’s attention quickly shifted towards the Borumba site. In early December, the Queensland government said it was set for crunch talks with Queensland Hydro to “save the project”, citing that its cost had increased to AU$18 billion and had been delayed by three years.

Alongside this, the government identified that there is less than a 1% chance that the project will be completed in time for its planned first power date of 2030. Instead, it is believed the project will be completed in July 2035.  In September 2024, a flurry of major contracts for the PHES project were signed with  AFRY-Aurecon Joint Venture, Water2Wire Joint Venture, and SYSTRA.

Read Next

July 27, 2026
Two Australian solar-plus-storage projects advance: Ark Energy secures AU$1.3 billion for 2.2GWh Richmond Valley project; Quinbrook submits 250MWp Queensland site.
July 24, 2026
Two weeks after announcing its acquisition of Harmony Energy, Swiss power firm Alpiq has unveiled its first large-scale battery project in its home country.
July 23, 2026
Spain has awarded €165 million to seven pumped hydro storage projects totalling around 2.1GW/21GWh, while Portugal has set a target of 1.4GW of new pumped hydro capacity by 2040.
July 23, 2026
The Clean Energy Investor Group (CEIG) has published a report calling on the Australian government to prioritise consistent and timely implementation of the reformed Environment Protection and Biodiversity Conservation (EPBC) Act.
July 22, 2026
Samsung C&T Renewable Energy Australia has submitted the 1GWh Boro solar-plus-storage project in New South Wales to Australia’s EPBC Act.