Arizona utility Tucson Electric Power (TEP) claims that the cost-effectiveness of a new large-scale solar-plus-storage facility under construction will allow it to provide “more solar energy to more customers for less money”.

TEP said that a 100MW solar PV array coupled with a 30MW/120MWh energy storage system will be completed and connected by the end of 2019. The utility said output from the solar farm would be purchased at a “historically low price”. An affiliate of NextEra Energy, which only last month said it will build another 10MW lithium-ion battery energy storage system in Arizona for utility Salt River Project, will construct the system.

According to TEP, the utility will be able to source renewable power for less than three cents per kilowatt-hour from the combined installation for a 20-year period. However, the utility said that the price, which was the only figure quoted in its announcement of the project, excluded the cost of the energy storage system. Nonetheless, TEP said that this was less than half the sum agreed under “similar contracts” in the past few years.

“This new local system combines cost-effective energy production with cutting edge energy storage, helping us provide sustainable, reliable and affordable service to all of our customers for decades to come,” TEP senior director for renewable energy and energy supply Carmine Tilghman said.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Announcement feeds into state-wide debate over cost of rooftop solar

While the project announcement appears to be exciting news for Arizona, following on the heels of news of three much smaller utility-scale energy storage systems by TEP, it has a slightly more, potentially, controversial side to it.

Currently there is a dispute over the cost of and compensation for rooftop solar power ongoing in the state. TEP itself has proposed a new rates structure for rooftop solar customers that would cut solar credits and instate time-of-use (ToU) rates earlier this month.

TEP argues that ‘community’ projects such as the 100MW PV + 120MWh storage system could be a more effective way to increase the utility’s share of renewable energy than relying on individual customers choosing to go solar. According to the utility, the plummeting cost of power from large-scale arrays compares unfavourably to rates paid for solar energy added to the grid by rooftop solar customers, which it says have increased in the last few years.

Arizona customers of TEP pay more than four times more for excess rooftop PV power than customers of other utilities, in other jurisdictions, the utility claimed.

“Focusing our resources on the development of cost-effective community scale systems allows us to provide more solar energy to more customers for less money. The best way to help solar grow in our community is by planning and siting systems in an organized, responsible and equitable manner,” TEP’s Carmine Tilghman said.

NextEra Energy Resources senior vice president of development Mike O’Sullivan said the project would create “good-paying jobs and increased tax revenue for the state and the local community”.

2 February 2027
The Tower Hotel, London, UK
Solar & Storage Finance Europe Summit brings together the developers, investors and lenders financing European solar and storage projects. As grid constraints, curtailment and weaker capture prices put pressure on returns, the summit explores what makes projects bankable, how co-located storage changes the revenue case and where capital providers see investable opportunities. Attendees can compare how their peers structure projects and meet people who could help them move their own projects or investments forward.
20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

November 20, 2026
Sodium-ion (Na-ion) is continuing to gain traction as a legitimate “major chemistry” — with CATL, BYD, and GM all committing to it — some developers, within and outside the US Na-ion space have argued that greater policy support should be directed toward advancing the technology.
Premium
November 19, 2026
As AI-driven data centre demand reshapes the US power landscape, BESS technology providers at RE+ highlighted an unexpected competitive advantage.
November 19, 2026
The Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) has been a popular topic of discussion at RE+ 2026 in Las Vegas, Nevada, US.
November 18, 2026
Energy-Storage.news speaks with LG Energy Solution Vertech chief product officer Tristan Doherty at RE+ 2026.
November 18, 2026
EsVolta has completed over US$180 million in financing for BESS projects in Texas, while Fluence has won a 200MWh project there.