AES completes phase one construction of largest solar-plus-storage project in the US

LinkedIn
Twitter
Reddit
Facebook
Email

Power company AES Corporation has completed construction of the 1,000MW Bellefield 1 project in Kern County, California. The overall project includes 500MW of solar and 500MW/2,000MWh of battery storage.

Bellefield 1 is part of Bellefield, a two-phase project, each consisting of 500MW of solar and a 500MW four-hour battery energy storage system (BESS).

Once Bellefield is completed, the 2,000MW project – 1,000MW solar and 1,000MW/4,000MWh BESS – is expected to be the largest solar-plus-storage facility in the US.

The project has a 15-year power purchase agreement (PPA) with Amazon.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The Bellefield project was acquired by AES from project developer Avantus in 2023.

AES says that more than 700 union jobs were created during the construction of Bellefield 1 and that approximately 1,000 union jobs are expected to be created at the peak of construction of Bellefield 2.

The company also expects significant earnings from placing Bellefield 1 in service in the second half of 2025. Construction on Bellefield 2 is scheduled to be completed in 2026.

To assist in construction, AES used Maximo, its ‘AI-enabled robotic system’, which the company says improved the safety, speed and accuracy of solar module installation.

Maximo is a robotic arm that performs solar panel installation, in what AES claims is half the time and cost.

As recently reported by Energy-Storage.news, AES’ financial results revealed that the company is contracting with US or South Korean suppliers for approximately 80% of its 2026 and 2027 battery needs.

Additionally, the company disclosed that it has imported all the batteries required for its upcoming projects this year.

From this information, it seems that AES is well-positioned to bring online Bellefield 1 and complete the construction of Bellefield 2 as scheduled.

Once the project is fully operational, it will overtake the Edwards & Sanborn project, also in California, as the the largest solar-plus-storage project in the US.

Andrés Gluski, president and CEO of AES said of Bellefield 1: “Completing the first 1,000 MW of Bellefield demonstrates how rapidly solar and storage can be deployed to meet the growing energy demand of data centres.”

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

July 29, 2025
Energy storage developer and system integrator Energy Vault has successfully closed a US$18 million financing for its Cross Trails battery energy storage system (BESS) project in Scurry County, Texas, US.
July 29, 2025
Spanish energy firm Zelestra and Portuguese utility EDP have signed what they call the “first” solar-plus-storage power purchase agreement (PPA) in the Spanish renewables market.
July 29, 2025
The New South Wales government has announced plans to launch a new tender seeking 500MW of firming capacity, seeking bids from battery energy storage, gas and virtual power plants (VPP).
Premium
July 28, 2025
Independent power producer (IPP) Arevon Energy CEO, Kevin Smith, speaks with Energy-Storage.news Premium about the importance of community engagement in developing BESS projects.
July 28, 2025
Lithium-ion battery storage system integrator Fluence and independent power producer (IPP) Invenergy will be partnering on the 475MW solar and 1,900MWh energy storage Hashknife Solar Energy Centre in Navajo County, Arizona, US.

Most Popular

Email Newsletter