20MW UK storage project to deliver millions in revenue from balancing services

January 27, 2017
LinkedIn
Twitter
Reddit
Facebook
Email

Image: METKA EGN.
A 20MW energy storage project co-located with gas/diesel fired generation, to be completed in March, will deliver millions of pounds in revenue from balancing services to the national transmission network.

The Noriker Power Staunch project will be completed for Hazel Capital, which recently awarded the EPC contract to METKA EGN and will use 40 LG Chem batteries installed alongside the fossil fuel generation assets in Newcastle-under-Lyme.

The project won a two year firm frequency response (FFR) contract with National Grid, which is expected to deliver c. £2.6 million (US$3.26 million) in revenues for each of the two years contracted.

The FFR contract is estimated to represent around 70% of total revenues in each of the first two years of the project’s life.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It also won a 15-year capacity market contract in the December 2015 T-4 auction which will begin in 2019. The contract price is £18,000/MW per year at 2014/15 prices and is therefore subject to be inflated by RPI (Retail Price Index) for the intervening period.

Further revenues will be accrued from Triad payments, where the installation will be used to avoid peak transmission network use charges, and electricity sales generated effectively as a by-product of creating the revenues from FFR and Triads.

The project, expected to cost £9 million to complete, is intended to deliver over £10.3 million from FFR and capacity market payments alone, in addition to Triad and other revenue streams.

This energy storage project follows the successful completion of a larger development in Puerto Rico by METKA EGN, which delivered a 57.65MWp solar farm alongside 20MW storage capacity. Renewable energy projects in Puerto Rico must comply with minimum technical requirements (MTR) to allow for their integration into the island’s grid. Developers must provide the equivalent to 30% of its nameplate capacity in storage for frequency regulation over a 10-minute duration. They must also provide 45% of the equivalent to the system’s nameplate, for one-minute ramping, with many in the industry viewing Puerto Rico as an ideal proving ground for the case for solar-plus-storage.

According to METKA EGN director Lefteris Pliakos, building on this experience will be a key focus for the company’s activity in the UK, as well as chasing opportunities for private power purchase agreements, when subsidies for large scale solar come to an end on 31 March.

Read Next

November 21, 2025
In a major week for European BESS deal-making, project acquisition and financing deals have been done in the Poland, Germany, Finland, the UK and Romania for grid-scale projects totalling well over 1GW of capacity.
November 19, 2025
Swedish renewable energy developer OX2 has formally taken ownership of the 1.2GW Dinner Hill Wind Farm and the co-located 400MWh Harvest Battery Energy Storage System (BESS) in Western Australia.
November 17, 2025
Rondo Energy and SCG Cleanergy have commenced operation of Southeast Asia’s first industrial thermal battery energy storage system (BESS) at SCG’s cement plant in Saraburi, Thailand.
November 17, 2025
Australia’s DCCEEW has announced that the Capacity Investment Scheme Tender 8 will launch later this month seeking 16GWh of energy storage.
November 14, 2025
BESS and flexible generation provider Statera Energy has secured £235 million (US$309 million) in debt financing for its 680MW/1,360MWh Carrington BESS project in Manchester, UK.