1,200MWh solar-plus-storage project in New South Wales, Australia, seeks approval

LinkedIn
Twitter
Reddit
Facebook
Email
Acen Australia owns a number of solar PV projects in NSW, such as the 936MWdc New England solar project (above). Image: ACEN Australia.

Renewable energy developer Acen Australia has submitted assessment documents for its 600MW Birriwa solar-plus-storage in New South Wales (NSW), Australia, which will incorporate a co-located 600MW/1,200MWh battery energy storage system (BESS).

The project developer is seeking approval via the Federal government’s Environment Protection and Biodiversity Conservation Act (EPBC).

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The project is set to be developed on an area of approximately 1,200 hectares consisting of mostly cleared grazing land, about 20km southeast of Dunedoo, in the NSW Central-West Orana region, the location of one of the Renewable Energy Zones (REZ) being developed in the state. The REZ recently transitioned into the delivery phase, as reported by our sister site PV Tech.

Acen Australia said the BESS will enable excess electricity generated by the PV facilities to be captured and released during periods of high demand. The system will also provide grid stability services and backup capacity to ensure the security of supply.

According to documents observed on the EPBC website, the project will look to install approximately one million solar PV modules and associated mounting infrastructure. The site will also include an on-site substation with a connection voltage of up to 500kV.

Construction of the project, which will have an average workforce of 360 throughout the development phase, will last 28 months, with the construction of the BESS expected to take around 16 months. Throughout operations, a workforce of up to 20 people will be required.

It is worth noting that the Birriwa solar-plus-storage project will be located next to two other solar projects developed by Acen Australia, as seen in the image above. These are the 400MW Stubbo solar PV project, at which construction began in November 2022, and the 320MW Narragamba solar project. These projects will connect to new transmission infrastructure developed by the Energy Corporation of NSW (EnergyCo) as part of the Central-West Orana REZ.

Once the Birriwa solar project receives approval, it will be able to transition into the construction phase. It will connect to the Merotherie Energy Hub and the transmission line proposed by EnergyCo NSW.

This article first appeared on our sister site PV Tech.

Read Next

February 13, 2025
Wind developer WestWind Energy has signed a lease agreement with Australia’s New South Wales government for the development of a 1,500MWh wind-plus-storage site in the south-west of the state.
February 13, 2025
ACE Power has submitted a 500MW BESS in Queensland to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act.
February 12, 2025
Europe’s energy storage industry and key stakeholders arrive in London for the 2025 Energy Storage Summit EU in just a few days.
February 12, 2025
Australian energy major AGL Energy disclosed in its half-year results that it intends to make a final investment decision (FID) over the next 18 months for 1.4GW of utility-scale battery energy storage systems (BESS).
February 12, 2025
Gold Green Energy has secured consent for a 400MWh solar-plus-BESS site, whilst AEMO has seen 18.1GW of BESS seeking a connection to the NEM.

Most Popular

Email Newsletter