1,200MWh solar-plus-storage project in New South Wales, Australia, seeks approval

LinkedIn
Twitter
Reddit
Facebook
Email
Acen Australia owns a number of solar PV projects in NSW, such as the 936MWdc New England solar project (above). Image: ACEN Australia.

Renewable energy developer Acen Australia has submitted assessment documents for its 600MW Birriwa solar-plus-storage in New South Wales (NSW), Australia, which will incorporate a co-located 600MW/1,200MWh battery energy storage system (BESS).

The project developer is seeking approval via the Federal government’s Environment Protection and Biodiversity Conservation Act (EPBC).

The project is set to be developed on an area of approximately 1,200 hectares consisting of mostly cleared grazing land, about 20km southeast of Dunedoo, in the NSW Central-West Orana region, the location of one of the Renewable Energy Zones (REZ) being developed in the state. The REZ recently transitioned into the delivery phase, as reported by our sister site PV Tech.

Acen Australia said the BESS will enable excess electricity generated by the PV facilities to be captured and released during periods of high demand. The system will also provide grid stability services and backup capacity to ensure the security of supply.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

According to documents observed on the EPBC website, the project will look to install approximately one million solar PV modules and associated mounting infrastructure. The site will also include an on-site substation with a connection voltage of up to 500kV.

Construction of the project, which will have an average workforce of 360 throughout the development phase, will last 28 months, with the construction of the BESS expected to take around 16 months. Throughout operations, a workforce of up to 20 people will be required.

It is worth noting that the Birriwa solar-plus-storage project will be located next to two other solar projects developed by Acen Australia, as seen in the image above. These are the 400MW Stubbo solar PV project, at which construction began in November 2022, and the 320MW Narragamba solar project. These projects will connect to new transmission infrastructure developed by the Energy Corporation of NSW (EnergyCo) as part of the Central-West Orana REZ.

Once the Birriwa solar project receives approval, it will be able to transition into the construction phase. It will connect to the Merotherie Energy Hub and the transmission line proposed by EnergyCo NSW.

This article first appeared on our sister site PV Tech.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 25, 2026
Recently, US BESS companies Energy Vault and Goshe, SMT Energy and Climate Adaptive Infrastructure, and NeoVolta and SK On have made major deals and secured strategic partnerships.
September 25, 2026
ESR, a Singapore-headquartered real asset owner and manager focused on logistics real estate and data centres, has signed an agreement to acquire 100% of Aquila Clean Energy APAC.
September 25, 2026
AEMO has said that a record 9.1GW of new renewable energy and storage capacity connected to the National Electricity Market (NEM) in FY26.
September 24, 2026
Market research firm Wood Mackenzie stated that data centre buildout is uplifting the US battery energy storage system (BESS) outlook across all segments.
September 24, 2026
Two Victorian battery storage projects have reached new construction and commissioning milestones this week, both connecting to the National Electricity Market (NEM) in Australia.