‘Considerable confidence’ in UK storage projects as they win 15-year contracts

December 9, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

Image: National Grid.
The number of battery storage projects to have won 15-year contracts in the latest Capacity Market auction is a sign of “considerable confidence” in the technology, according to the director of the Electricity Storage Network.

The results of the latest T-4 auction published this morning show that contracts totalling 3.2GW have been awarded to storage projects, with a proportion expected to be met with batteries.

In a departure from normal results in which the technology fails to gain more than a four year contract, a number of projects ranging in size have successfully secured long term contracts usually awarded to other projects classed as new or existing generators.

Speaking to Energy Storage News this morning, Anthony Price, director of the UK’s Electricity Storage Network, said the results showed a step-change in confidence in the technology.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“There was no reason why storage could not participate in the long term contracts [but] some folk in the industry didn’t feel necessarily comfortable [that] storage technologies had matured sufficiently.

“But with significant changes that have taken place in the industry over the last couple of years, I think that a number of providers have become more comfortable with the idea of storage taking part,” he said.

“The significance is [that] without any greater clarity on the technical requirements of the capacity market, the bidders in the long-term market have expressed considerable confidence [and] are prepared to take a risk on how they will be deployed.”

Four of the projects to win under National Grid’s recent EFR tender – 10MW Cleator and 40MW Glassenbury projects by Low Carbon; EDF’s 49MW West Burton site; and the 10MW Blackburn Meadows project by E.ON UK – were successful in this week’s auction, which according to Price is a further sign of interest and confidence in battery storage.

He said: “The tender results show that people are prepared to invest money against a known income stream and if they can then add on the Capacity Market payment then it looks to be quite an attractive business opportunity, which is what the industry has been saying for a long time.”

James Court, head of external affairs at the UK’s Renewable Energy Association, added: “Following the success of the National Grid EFR, this is another impressive step forward for energy storage and should give government, industry and investors confidence.

“The fact that storage has bid competitively demonstrates it is already commercial, and has the flexibility to provide multiple services which can lead to separate income streams, making the financial case for storage even more compelling.”

Despite this confidence, Price expressed some concern over the continuing lack of clarity regarding the regulations governing the Capacity Market, which remain consistently vague. They do not outline the requirements of winning projects in how to meet the possible demands of a ‘Capacity Market event’ in which providers must supply energy at times of system stress.

Price warned that there is no clarity over how contract winners are intending to use their batteries to meet these requirements, which could potentially last several hours.

Therefore, despite this significant moment for UK battery storage, he is advocating for continued pressure on policy-makers to provide greater clarity and rules in the capacity market that recognise the value of storage.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

March 3, 2026
3.6GWh of solar-plus-storage developments have progressed in Australia this week, with Edify Energy partnering with DT Infrastructure and Flow Power acquiring a 60MW project.
March 3, 2026
A second-round auction in the UK for grid stability services, including inertia, concluded without any wins for grid-forming battery energy storage system (BESS) projects.
March 3, 2026
Allianz GI, Luxcara and Return have acquired BESS projects and portfolios in Germany, Finland and Spain; Low Carbon, OX2, Cero Generation and Revera have taken FIDs on projects in Poland, Finland and the UK; and NHOA Energy has received a 600MWh order in Italy. All in all, the projects total at least 3.7GWh of capacity.
March 3, 2026
A number of Chinese energy storage companies have released their 2025 annual earnings results and forecasts, revealing divergent performance.
Premium
February 27, 2026
We caught up with the CEO of owner-operator BW ESS, Erik Strømsø, about the firm’s next deployment plans, tolling trends, procurement and LDES, with its 11.5-hour Bannaby BESS in Australia further proof of lithium-ion’s long-duration potential.