Two more US utilities make major gas, solar and storage plans

By John Parnell
LinkedIn
Twitter
Reddit
Facebook
Email
TVA offices in Chattanooga, Tennessee. Source: Flickr/Tennessee Valley Authority

Utilities in New Mexico and Tennessee have both released plans for new solar, storage and gas infrastructure.

The New Mexico plan is more immediate as it is linked to the closure of the San Juan coal power station in June 2022. The utility PNM has asked the state’s regulator to approve “the securitization of the unrecovered investment in the plant” and backing for replacement infrastructure.

It has suggested 280MW of gas peaker plants, 350MW of solar and 130MW of battery storage.

The plan is the result of PNM’s modelling. Compared to the continuation of operations at San Juan it expects to save customers US$7.11 per month in 2023.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Each step we take toward 100% emissions-free must balance the cost, the environment, and reliability,” said Pat Vincent-Collawn, chairman, president and CEO, PNM Resources the parent company of utility PNM. “The San Juan replacement plan we put forth will not only save customers money but will have one of the largest solar facilities in the US and one of the highest percentages of battery storage anywhere in the country.”

Meanwhile, the Tennessee Valley Authority (TVA) has filed its latest Integrated Resource Plan. The utility’s 20-year plan includes up to 2.4GW of energy storage by 2028 and up to 5.3GW by 2038. It suggests a range of 1.5-8.0GW of new solar capacity by 2028 and 14GW by 2038.

The rollout of that energy storage pipeline will be dependent on the cost reductions achieved in the sector. The IRP states: “The trajectory and timing of additions will be highly dependent on the evolution of storage technologies.”

The figures include utility-scale and distributed solar and storage installs as appropriate. While various scenarios were mapped out, “solar expansion plays a substantial role in all futures”, according to TVA.

“The 2019 IRP emphasizes the importance of flexibility in our generation in response to the changing energy marketplace,” said Laura Campbell, TVA vice president of enterprise planning. “TVA looked at a wide range of possible futures, and flexibility is important in every case to ensure a reliable power supply.”

As well as planned coal closures, a further 2.2GW of coal capacity is being considered for retirement.

Gas-fired additions will be dependent on the scale of solar deployment with up to 8.6GW of peaker capacity could be built. As such as 9.8GW of combined cycle gas could also be built by 2038.

The combination of solar and storage is increasingly competitive with gas generation.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

Premium
October 30, 2026
How should BESS owner-operators be thinking about augmentation of their projects further down the line?
Premium
October 30, 2026
Few grids illustrate the strain of America’s data centre boom more starkly than the PJM Interconnection.
October 29, 2026
The California Energy Commission (CEC) has released over US$46 million for the state’s Distributed Electricity Backup Assets (DEBA) Programme.
October 29, 2026
Distributed energy resource (DER)-focused company FranklinWH has recently announced advancements in residential energy storage programmes in Louisiana and Iowa.
October 28, 2026
Energy storage developer-operator Bimergen Energy has filed an application for an Option 2 Retail Electric Provider (REP) certificate in Texas, US.