Storage projects secure 3.2GW in UK’s Capacity Market

LinkedIn
Twitter
Reddit
Facebook
Email

Image: S&C Electric.
Storage projects have landed more than 3.2GW of contracts in the provisional Capacity Market auction results.

This week’s auction secured around 52GW of electricity capacity for the winter 2020/21 period and storage – competing for the first time – landed more than 6% of the total allocated capacity.

Most notably four of the battery projects previously successful within National Grid’s Enhanced Frequency Response (EFR) tender also gained 15-year contracts as new build generators in this week’s Capacity Market auction, further endorsing their application for grid stability.

Those four projects are the 10MW Cleator and 40MW Glassenbury projects undertaken by Low Carbon, the 49MW West Burton site being developed by EDF Energy Renewables and the 10MW Blackburn Meadows project being constructed in Sheffield by E.ON UK.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The results also show that some of the unsuccessful EFR projects have also been accepted within the capacity market, such as Centrica’s 48MW Roosecote projects which was also awarded a long-term contract.

I count 28 new-build battery projects getting Capacity Market agreements – totalling 501MW. Only 1 battery failed to get an agreement.— Jonathan Davison (@_jonnydavison) December 9, 2016

UK business and energy secretary Greg Clark welcomed the results, lauding the auction’s potential to secure electricity “years in advance”.

“Technological innovation, as part of our low carbon future, will create jobs and opportunities across the UK. We are rebuilding an archaic energy system, bringing forward brand new gas power and innovative low-carbon capacity like battery storage to upgrade our energy mix.

“This is about more than just keeping the lights on. A modern, reliable, and flexible electricity system powers the economy and Britain’s future success,” he added.

But while the results are a positive step forward for battery storage, the lower-than-anticipated clearing price of £22.50/kW have proven not enough to incentivise new-build combined cycle gas turbine generators which are essential to the government’s energy strategy. This was reflected by the capacity awarded to existing generators, which stands at just over 84%.

Jonathan Marhsall, energy analyst at the Energy and Climate Intelligence Unit, said the low clearing price suggested that the market considers there to be “more than enough capacity” in the system already.

“Only considering peak load capacity, the current system is often skewed to less efficient technologies that are good for short runs over the winter, but not a sensible long-term plan for the electricity network.

“Making small changes in the system, mirroring policies in both the US and across Europe to prioritise low-carbon flexibility tools such as demand side response and storage could not only keep bills down, but would increase the ease of the ongoing transition to a low-carbon system with renewables at the core,” he said.

The results remain provisional until 20 December 2016.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

September 16, 2026
Recent moves from the US federal government could prove more damaging to US renewable energy deployment than foreign entity of concern (FEOC) compliance requirements, according to legal and industry experts.
Premium
September 16, 2026
On 26 August, US President Donald Trump banned the import of inverters, transformers and other power equipment citing a potential risk to US grid security, via emergency executive order (EO).
September 15, 2026
Massachusetts Governor Maura Healey has released a comprehensive framework establishing principles and expectations for responsible data centre development in the state.
September 14, 2026
Heron Power and NeoVolta have secured significant credit facilities, while Carina Energy has launched a FEOC compliance support practice to help developers navigate increasingly complex regulatory requirements.
September 14, 2026
UAE state-owned renewables company Masdar has partnered with Germany’s Luxcara for battery storage and wind energy projects.