Spanish government awards €360 million for co-located battery storage projects

LinkedIn
Twitter
Reddit
Facebook
Email

The Spanish Ministry of Ecological Transition (MITECO) has awarded €360 million (US$415 million) to 1.14GW of solar PV co-located with battery energy storage system (BESS) projects.

Although the programme, called RENOINN 2, was open to other technologies co-located with BESS, solar PV accounted for nearly the entire volume awarded, 1.22GW. In total, the programme allocated €433 million in funding to 524 renewable energy projects co-located with BESS, of which 463 were co-located with solar PV.

On the BESS front, the programme awarded 2.3GWh of energy storage capacity, eight times the awarded capacity (351.6MWh) in the first iteration of the programme.

The goal of the programme was to support the development of innovative technologies, including agrivoltaics (agriPV) and floating solar (FPV) co-located with BESS.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In total, the RENOINN 2 programme awarded projects under five different lines, one for agricultural land, one for FPV, one for infrastructure, one for self-consumption and the last one for renewable heat pump installations.

AgriPV accounted for the majority of the solar PV projects awarded, with 882MW, while 1.7GWh of BESS was awarded under that category. These were divided into three sub-categories depending on the type of installation and the distance from the crop.

MITECO said that half of the agriPV projects awarded funding were on farms dedicated to cereals and tree crops such as olive groves and orchards, among others. For these projects, the solar PV panels will be mounted on a structure more than four meters high.

Most of the agriPV projects awarded will include a control plot to analyse the results and effects of solar PV panels with crops.

Moreover, a total of 29 FPV projects were awarded funding for a combined installed 46MW of solar PV and  51MWh BESS, while the solar self-consumption category had 70MW of combined solar PV capacity and 150MWh of BESS across 274 projects.

Similar to previous funding of renewable energy projects, both upstream and downstream, the funds will be provided through Spain’s recovery and resilience plan (PRTR) under NextGenEU

The full list of awarded projects can be accessed here.

Per region, Catalonia has been awarded the most solar PV across all five funding lines, with 322MW. It is followed by Castile and León with 208MW and the Valencian Community with 158MW, as shown in the chart below.

This story first appeared on PV Tech.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 17, 2026
ASX-listed Frontier Energy has started construction on Stage 1 of its Waroona Renewable Energy Project in Western Australia (WA), which pairs solar PV with a battery energy storage system (BESS).
November 16, 2026
New York’s second competitive solicitation for large-scale energy storage has launched, seeking a gigawatt (1GW) of grid-connected resources.
November 13, 2026
West Arthur Energy, a project company owned by Western Australian developer Lacour Energy, has referred a wind generation site with a 4,000MWh battery energy storage system (BESS) to Australia’s EPBC Act.
November 11, 2026
Envision Energy will supply its Gen 8 BESS platform for ju:niz Energy’s 442MWh Smareg 13 project in Bavaria, Germany.
November 11, 2026
Delta and partner Samsung Vista C&I Australia have lodged an EIS for an 800MWh BESS at the Vales Point Power Station site in NSW.