RWE commissions Texas solar-plus-storage project

December 4, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

RWE Clean Energy has commissioned the Stoneridge Solar PV project in Texas, adding 200MW of solar PV and 100MW/200MWh BESS to its operational portfolio.

The company is the US arm of German power firm RWE, and completed work at the project in Milam County late last month. This is in line with a timeline proposed by RWE CEO Markus Krebber, who visited the site earlier this year, and announce that construction at the Stoneridge Solar project would be completed by the end of 2025.

The commissioning brings the company’s operational renewable energy capacity in the state, where ERCOT runs the grid, to above 4.8GW and the company’s Texas portfolio now accounts for close to half of its 11GW of energy generation capacity in operation in the US.

According to Krebber, the company has a pipeline of 4GW of renewable energy generation capacity currently under construction in the US.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“We are helping Texas and the nation secure their energy future with scalable, homegrown energy while also delivering meaningful benefits to communities across America’s heartland,” said RWE Clean Energy CEO Andrew Flanagan.

See the full original version of this article on PV Tech.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

February 26, 2026
Utility Xcel Energy will install 30GWh of US startup Form Energy’s iron-air batteries at a data centre in Pine Island, Minnesota, belonging to tech giant Google.
February 25, 2026
In this Energy-Storage.news roundup, FlexGen updates its EMS, LandGate launches a BESS site selection tool, ON.energy and Shoals target AI data centres, and Sunrun has a successful season of dispatching energy with PG&E.
Premium
February 25, 2026
In an interview with Energy-Storage.news Premium, Jay Jayasuriya, Principal at Sendero Consulting, argues that AI data centres are “convenient scapegoats” for grid failures
February 25, 2026
The 200MW/400MWh New England battery energy storage system (BESS) in New South Wales has registered with the Australian Energy Market Operator’s (AEMO) Market Management System (MMS).
February 24, 2026
D. E. Shaw Renewable Investments (DESRI) has signed a preferred equity investment in IPP Linea Energy’s 235MW/470MWh Duffy battery energy storage system (BESS) in Matagorda County, Texas.