Subsidy-free bifacial solar PV-plus-storage project completed in England

December 19, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
#SmartSolarStorage2020: GRIDSERVE said its new solar-plus-storage site is the first in the UK to include bifacial PV modules and single-axis trackers, as well as being unsubsidised. Image: GRIDSERVE.

Renewables developer GRIDSERVE has completed a “game changing” hybrid solar-plus-storage farm in York, UK, claiming it to be the first in the country to boast single-axis trackers and bifacial panels.

The site combined 37.4MWp of Suntech bifacial modules with 27MW of energy storage, using Nextracker single-axis trackers to shift the site’s generation portfolio into more beneficial hours.

The project is thought to be the most northerly combination of the two cutting edge technologies – bifacial panels and trackers – and the site ‘stacks’ a number of revenue streams in order to be financially feasible without subsidy support.

Toddington Harper, chief executive at GRIDSERVE, said that subsidy-free projects such as this demonstrate that the UK is capable of meeting its net zero obligations “well before 2050”.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

As we kick off the New Year, Energy-Storage.news and PV Tech will be talking #SmartSolarStorage2020. Use the official hashtag on your social media channels to join and follow the conversation.

To read the full version of this story, visit PV Tech.

Additionally, an in-depth project overview is included in PV Tech Power volume 21, published earlier this week. The journal, including that feature-length profile of the project, can be downloaded here (free, with some subscription details required).

Read Next

November 14, 2025
BESS and flexible generation provider Statera Energy has secured £235 million (US$309 million) in debt financing for its 680MW/1,360MWh Carrington BESS project in Manchester, UK.
Premium
November 13, 2025
On 4 September, US Immigration and Customs Enforcement (ICE), along with multiple other law enforcement organisations, raided Hyundai Motor and LG Energy Solution’s electric vehicle (EV) battery cell plant in Ellabell, Georgia, US.
November 13, 2025
The three-year rolling partnership, whereby CATL will supply HyperStrong with cells and system products, could be updated annually.
November 13, 2025
Statkraft, Kyon Energy and Juniz Energy have progressed BESS projects in Germany, all in all totalling a combined 213MWh of capacity.
November 13, 2025
Octopus Australia has achieved financial close on a AU$900 million (US$587 million) DC-coupled hybrid facility that combines 300MW of solar generation with a 243MW/486MWh battery energy storage system (BESS) in New South Wales.