Subsidy-free bifacial solar PV-plus-storage project completed in England

December 19, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
#SmartSolarStorage2020: GRIDSERVE said its new solar-plus-storage site is the first in the UK to include bifacial PV modules and single-axis trackers, as well as being unsubsidised. Image: GRIDSERVE.

Renewables developer GRIDSERVE has completed a “game changing” hybrid solar-plus-storage farm in York, UK, claiming it to be the first in the country to boast single-axis trackers and bifacial panels.

The site combined 37.4MWp of Suntech bifacial modules with 27MW of energy storage, using Nextracker single-axis trackers to shift the site’s generation portfolio into more beneficial hours.

The project is thought to be the most northerly combination of the two cutting edge technologies – bifacial panels and trackers – and the site ‘stacks’ a number of revenue streams in order to be financially feasible without subsidy support.

Toddington Harper, chief executive at GRIDSERVE, said that subsidy-free projects such as this demonstrate that the UK is capable of meeting its net zero obligations “well before 2050”.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

As we kick off the New Year, Energy-Storage.news and PV Tech will be talking #SmartSolarStorage2020. Use the official hashtag on your social media channels to join and follow the conversation.

To read the full version of this story, visit PV Tech.

Additionally, an in-depth project overview is included in PV Tech Power volume 21, published earlier this week. The journal, including that feature-length profile of the project, can be downloaded here (free, with some subscription details required).

Read Next

Premium
December 11, 2025
Energy-Storage.news Premium speaks with John Farrell, Co-Director of The Institute for Local Self-Reliance (ILSR), on rising utility costs and the role energy storage can play.
Premium
December 10, 2025
Last month was the first time since June that both pre-application submissions and full planning consent submissions for grid-scale UK BESS surpassed 1GWh – just before NESO announced the results of its grid connection queue reshuffle.
December 10, 2025
AFC and public-private-partnership (PPP) Cabeolica have inaugurated 13.5MW of wind power generation and 26MWh of battery storage in Cape Verde.
December 9, 2025
The 600MW/1.6GWh Melbourne Renewable Energy Hub has commenced commercial operations in Victoria, Australia.
December 9, 2025
The UK’s National Energy System Operator (NESO) will offer grid connection offers up to 2035 to 283GW of projects following a reform of the process.