Scotland’s first utility-scale battery brought online to deliver sub-second balancing

By David Pratt
LinkedIn
Twitter
Reddit
Facebook
Email
Helen Mahy, chairman of TRIG and Gavin McAlpine, chairman of RES, show Scotland’s minister for trade, investment and innovation, Ivan McKee, centre, around the Broxburn Energy Storage facility. Image: RES.

Scotland’s first utility-scale battery storage facility has been officially opened today, having begun delivering sub-second balancing services to National Grid at the end of June under a bespoke agreement secured before the hotly contested Enhanced Frequency Response (EFR) auction of 2016.

The 20MW Broxburn Energy Storage facility was built by RES, which had sold the project to The Renewables Infrastructure Group (TRIG) in August last year for £20 million. It was the first project to have been acquired by TRIG and RES’ fourth in the UK, with the company now managing the site.

Richard Crawford, director of infrastructure at TRIG’s investment manager InfraRed Capital Partners, said it was “an exciting day for the company” to see its first battery storage project completed.

Testing of the project, which uses batteries from Samsung SDI, commenced in May, enabling battery commissioning to be completed. This was followed by final testing under the EPC construction contract, which completed on 30 June when the battery began to deliver its contracted service to National Grid.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project had secured an initial four-year bespoke bilateral agreement to provide dynamic, two-way import and export sub-second balancing services to National Grid. Sister title Solar Power Portal was told in 2017 that revenues over the contract are substantially based on pre-determined, RPI-indexed availability payments.

Such a bespoke agreement was no longer available when National Grid moved to a tender auction model for EFR services, when almost 1GW of storage projects competed to win 200MW in available contracts.

Opening the site today, Scotland’s minister for trade, investment and innovation Ivan McKee said: “I am very pleased to have the chance to open the Broxburn Energy Storage project today, which is Scotland’s first sub-second response energy storage project.

“A welcome addition to Scotland’s low carbon energy system, projects such as this one can increase system flexibility and create opportunities for the further decarbonisation of Scotland’s economy.”

Both TRIG and RES added that the battery would allow for greater levels of renewable energy to be brought onto the UK’s energy system by helping to avoid the cost of new grid infrastructure.

Rachel Ruffle, RES’ managing director, said: “We believe that this project will play an important role in demonstrating this and will encourage policymakers and regulators to accelerate the removal of barriers to wider deployment of energy storage in the UK.”

Broxburn represents Scotland’s largest energy storage facility, with a 2MW battery installed at a power station in Orkney thought to be the next largest. This is followed by the 1MW/1.3MWh ‘Batwind’ project, connected to an offshore floating wind farm, which was brought online by Younicos in July this year.

8 September 2026
Barcelona, Spain
Battery & Energy Storage Tech Europe (BESTE) is Europe’s industrial scaling platform for stationary and industrial battery applications — not EVs. Taking place 8–9 September 2026 at Fira de Barcelona, BESTE brings together utilities, IPPs, energy-intensive industries, data centres, ports, rail, maritime, defence and aerospace OEMs — all deploying or integrating battery storage at scale. Over 100 companies already confirmed — including EDP Renewables, Acciona, Endesa, Naturgy, Neoen, Galp, Basquevolt and Veolia — alongside 40+ expert speakers and international institutional support from BEPA, BVES, LDES and Volta Foundation. Where Europe’s battery & ES ecosystem turns projects into reality.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

August 11, 2026
The Clean Energy Finance Corporation committed a record AU$9.1 billion (US$6 billion) in the financial year to 30 June 2026.
Premium
August 11, 2026
What led Field to submitting, and winning, 16- to 18-hour BESS projects in the UK’s long-duration energy storage (LDES) cap-and-floor scheme, and what are the next steps? We hear from the firm’s technical director.
August 7, 2026
ZEBRE has submitted the 180MW/360MWh Noblevale Battery in Queensland for federal environmental assessment under the EPBC Act.
August 6, 2026
Denmark-headquartered multinational energy company Ørsted has put its 250MW/500MWh Old 300 energy storage project in Needville, Texas, US into operation.
August 6, 2026
Australian Vanadium Limited has signed an MoU with Alcoa to evaluate the deployment of vanadium flow battery technology in Western Australia.