NEC to deliver brace of UK projects in latest contract wins

By David Pratt
LinkedIn
Twitter
Reddit
Facebook
Email
The 40MW Glassenbury battery is among the projects already delivered by NEC in the UK. Image: VLC Energy.

NEC Energy Solutions has been selected by the UK’s first listed fund targeting energy storage to deliver two projects totalling 19MW, including what could be the largest behind the meter installation in the country.

Gore Street Capital’s Energy Storage Fund acquired the Port of Tilbury and Lower Road projects from Origami Energy in September. They both had all land and grid access rights, planning and other consents necessary to start construction and enter operations upon acquisition.

NEC will carry out the EPC duties, supported by Nippon Koei (NK), to begin construction in December 2018 and January 2019 respectively, with commercial operations scheduled to start in mid‐2019.

Steve Fludder, chief executive of NEC Energy Solutions, said: “We couldn’t be happier with our role in the Gore Street Energy Storage Fund and we look forward to working with Gore Street Capital on future projects as they continue to build out their portfolio.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The first of the two projects will be co-located with London’s Port of Tilbury industrial port facility, Thames and at 9MW, the NEC GSS Grid Storage Solution would, on current comparisons, become the largest behind‐the‐meter battery storage system in the UK.

It will use a metering scheme, installed by NK, to enable the battery system to reduce the Port’s peak demand while integrating with existing renewable generation on site.

Meanwhile, the 10MW Lower Road project will be grid connected to provide front of the meter grid services. It will benefit from three revenue stream contracts including services to the capacity market, participating in TRIADs and providing dynamic firm frequency response services to National Grid.

The brace of projects was Gore Street’s first investment following the acquisition of the two seed assets in June 2018 and the IPO of the fund on 25 May 2018, when the fund secured £35 million of investment compared to a target of £100 million.

Alex O’Cinneide, chief executive of the fund’s investment adviser Gore Street Capital, said: “The EPC contracts are an important milestone in the commercialization process and we are delighted to have secured such a highly regarded partner.”

Gore Street’s batteries are the latest contract wins for NEC Energy Solutions in the UK, where it previously delivered a 50MW portfolio of projects for VLC Energy at the start of the year. A case study looking at the 10MW Cleator and 40MW Glassenbury projects in detail can be found here.

Read Next

October 15, 2026
Energy storage owner-operator Nightpeak Energy has reached financial close and commercial operation on its 150MW/300MWh Bocanova 2 battery storage project in Brazoria County, Southeast Texas.
October 14, 2026
The Illinois Power Agency (IPA) is seeking stakeholder feedback on its summer procurement of 600MW of energy storage projects in the US state, after falling short by 438MW.
October 13, 2026
Bankability & offtake and regulatory & system reform were the key talking points on the opening panel of the Battery Asset Management Summit UK & Ireland 2026 which runs today and tomorrow (13-14 October). 
October 13, 2026
US tax equity syndicator Foss & Company has closed a US$58 million partnership flip transaction to finance an energy storage project in Hidalgo County, Texas, developed by GridStor.
October 13, 2026
Independent power producer (IPP) Clearway Energy has added 210MW of energy storage capacity to its Honeycomb Energy Centre fleet in Southern Utah, US.