New Zealand’s first grid-scale battery storage system project nears start of construction

LinkedIn
Twitter
Reddit
Facebook
Email
Infratec rooftop solar-plus-battery project in the Cook Islands, commissioned in early 2020. Image: Infratec.

Power distribution company WEL Networks and renewables developer Infratec are in the final stages of assessment for what will be New Zealand’s first utility-scale battery energy storage system (BESS). 

WEL Networks, one of 29 electricity distribution entities in the country, said that the 35MW project in the Waikato District of New Zealand’s upper North Island is being readied for construction and is expected to be commissioned by October 2022.

New Zealand has a national net zero by 2030 policy goal and WEL Networks said the Waikato BESS will be designed to serve the entire electricity value chain, from allowing for more renewable energy to be installed and connected to the grid, storing solar and wind energy, to strengthening local electricity supply reliability and delivering fast reserve to correct supply and demand imbalances. 

According to WEL Networks chief executive Garth Dibley, the project will cost around NZ$25 million (US$17.66 million) and has received resource consent under New Zealand’s Resource Management Act, a “huge milestone” for WEL, he said. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“This technology will help network resilience while supporting renewable generation uptake,” Dibley said, adding that the battery will support the charging of electric vehicles (EVs), maximise the benefits of solar power and provide back up during grid emergencies. 

Nick Bibby, general manager for business development at Infratec said his company will lean on its experience in international battery development to develop and deliver the 35MW BESS.

“Batteries will need to be embedded in networks to best serve local communities. We have selected a mature technology with a 20-year life span, so we expect this battery to be making headlines for all the right reasons for years to come,” Bibby said.  

Infratec’s BESS projects to date include commercial and industrial (C&I) battery projects in New Zealand, and solar-plus-storage and microgrid systems across Pacific Islands of Tonga, the South Cook Islands, Micronesia, Nauru, Kiritimati and others. 

The company has said it believes New Zealand needs large-scale battery storage urgently to complement renewable energy growth and pumped hydro plants, as well as to back up large interconnectors between the country’s North and South Islands. 

Read Next

Sponsored
July 28, 2026
We caught up with Kevin Huang, Senior Vice President and President of Energy Storage Product Line at Envision Energy at Smarter E in Munich for a video interview on the company’s energy storage strategy and the growing role of AI data centres in power demand.
July 28, 2026
Malawi’s energy minister was on hand last week as the southeast African country inaugurated its first large-scale standalone battery energy storage system (BESS).
July 28, 2026
The government of Malaysia has unveiled the next round of its Large-scale solar (LSS) program tender seeking 2.5GW of solar PV co-located with 1.25GW of battery energy storage system (BESS) capacity.
July 23, 2026
Spain has awarded €165 million to seven pumped hydro storage projects totalling around 2.1GW/21GWh, while Portugal has set a target of 1.4GW of new pumped hydro capacity by 2040.
Sponsored
July 22, 2026
We caught up with Michael Koller, Solutions Director for Europe and the UK with Envision Energy, at this year’s Smarter E Europe trade show in Munich.