Mixed Q3 for Fluence: revenue and guidance down but orders and profits up

August 8, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Battery energy storage system (BESS) integrator Fluence had a mixed third financial quarter, with a revenue fall and a narrowing down of its full-year guidance, but a record quarterly intake and increased profit margins.

The company’s financial year runs to 30 September, making the three months to 30 June its Q3, and revenues in the period fell 10% year-on-year to US$483.3 million.

Fluence said the revenue fall was down to the ‘timing of product deliveries’, the same reason it gave for a revenue fall in its Q2 (January-March). The same happened with numerous other system integrators, and most sources have said this is largely down to delays in getting BESS projects online in the US due to supply chain and grid infrastructure completion issues.

The trend appears to have affected its full-year performance too, with the company narrowing down – though not reduce the bottom end of – its revenue guidance. It is revising its full-year forecast to US$2.7-2.8 billion from US$2.7-3.3 billion previously, and its adjusted EBITDA to US$55-65 million from US$50-80 million previously.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, the company’s profit margins improved in the quarter, with its GAAP gross profit margin more than quadrupling to 17.2%, a net income of US$1.1 million versus a US$35 million loss the previous year and adjusted EBITDA of US$15.6 million versus negative US$27.5 million a year prior. It also saw its quarterly order intake more than double year-on-year to US$1.3 billion leaving it with a backlog of US$4.5 billion, a record.

Fluence is one of the world’s largest BESS providers globally by projects deployed and contracted and also has a strong digital offering, which will have brought its annual recurring revenues (ARR) to US$100 million by the end of the financial year.

The firm also revealed recently that it will provide 2.2GWh of BESS to asset owner Excelsior for US projects that will qualify for domestic content investment tax credit (ITC) incentives under the Inflation Reduction Act (IRA).

In its Q3 presentation, it explained that using using cells and modules that are manufactured in the US will enable it to ‘easily’ meet the domestic content thresholds required for BESS. The threshold starts at 40% for 2025, and US-made cells comprise 38% and modules (packaging) comprises 3.3%, pushing it over the line. A thermal management system is 4.9%, battery management system (BMS) 5.2% and production of the overall battery pack is another 21%.

It said it expects deliveries of US-made cells from supplier AESC to start in December 2024, ramping up over the course of 2025. It’s not clear if that is the same supplier for the Excelsior deal, which it didn’t name but said would be from a factory in Tennessee, while AESC’s announced gigafactory is in neighbouring Kentucky.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 19, 2026
“When we started back in two years ago, there was a lack of understanding in the market about how the grid-forming inverters operate,” said Ghasem Jahedi, principal grid engineer at AGL.
March 19, 2026
Energy-Storage.news speaks to Dr. Kai-Philipp Kairies, CEO and co-founder of ACCURE Battery Intelligence, ahead of the upcoming Energy Storage Summit USA 2026.
March 19, 2026
In this US news roundup, updates on solar-plus-storage projects from Google and DTE Energy, Sunraycer, Invenergy and SRP, Idemitsu Renewables, and Clēnera.
Premium
March 19, 2026
The price of BESS has fallen steadily in the past few years, but recent events look set to slow or event reverse that trend at least in the short term. Video interviewees at last month’s Energy Storage Summit 2026 shared their views on the topic.
March 18, 2026
LG Energy Solution has entered into a US$4.3 billion supply agreement with Tesla, announced by the US government, while simultaneously upgrading its EV battery plant with GM for ESS cells.