Battery energy storage system (BESS) integrator Fluence had a mixed third financial quarter, with a revenue fall and a narrowing down of its full-year guidance, but a record quarterly intake and increased profit margins.

The company’s financial year runs to 30 September, making the three months to 30 June its Q3, and revenues in the period fell 10% year-on-year to US$483.3 million.

Fluence said the revenue fall was down to the ‘timing of product deliveries’, the same reason it gave for a revenue fall in its Q2 (January-March). The same happened with numerous other system integrators, and most sources have said this is largely down to delays in getting BESS projects online in the US due to supply chain and grid infrastructure completion issues.

The trend appears to have affected its full-year performance too, with the company narrowing down – though not reduce the bottom end of – its revenue guidance. It is revising its full-year forecast to US$2.7-2.8 billion from US$2.7-3.3 billion previously, and its adjusted EBITDA to US$55-65 million from US$50-80 million previously.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

However, the company’s profit margins improved in the quarter, with its GAAP gross profit margin more than quadrupling to 17.2%, a net income of US$1.1 million versus a US$35 million loss the previous year and adjusted EBITDA of US$15.6 million versus negative US$27.5 million a year prior. It also saw its quarterly order intake more than double year-on-year to US$1.3 billion leaving it with a backlog of US$4.5 billion, a record.

Fluence is one of the world’s largest BESS providers globally by projects deployed and contracted and also has a strong digital offering, which will have brought its annual recurring revenues (ARR) to US$100 million by the end of the financial year.

The firm also revealed recently that it will provide 2.2GWh of BESS to asset owner Excelsior for US projects that will qualify for domestic content investment tax credit (ITC) incentives under the Inflation Reduction Act (IRA).

In its Q3 presentation, it explained that using using cells and modules that are manufactured in the US will enable it to ‘easily’ meet the domestic content thresholds required for BESS. The threshold starts at 40% for 2025, and US-made cells comprise 38% and modules (packaging) comprises 3.3%, pushing it over the line. A thermal management system is 4.9%, battery management system (BMS) 5.2% and production of the overall battery pack is another 21%.

It said it expects deliveries of US-made cells from supplier AESC to start in December 2024, ramping up over the course of 2025. It’s not clear if that is the same supplier for the Excelsior deal, which it didn’t name but said would be from a factory in Tennessee, while AESC’s announced gigafactory is in neighbouring Kentucky.

Read Next

August 8, 2025
Lyten’s deal to acquire and recommence operations of European battery firm Northvolt out of bankruptcy has winners and losers, but some of the challenges that led to its demise have already been solved.
August 8, 2025
Utility Portland General Electric (PGE) announced the completion of three battery energy storage systems (BESS) totalling more than 1.9GWh in Portland, Oregon, US.
August 8, 2025
Ampyr Australia has officially started construction on its 300MW/600MWh Wellington Stage 1 BESS in New South Wales.
August 7, 2025
Energy storage developer and system integrator Energy Vault has received approval to pursue market-based participation in the California Independent System Operator (CAISO) with the Calistoga Resiliency Centre (CRC).
August 7, 2025
Calibrant, a joint venture between Green Investment Group and German engineering company Siemens, has energised and begun generating Value of Distributed Energy Resources (VDER) credits from three front-of-the-meter battery energy storage systems (BESS) in New York, US.

Most Popular

Email Newsletter