Microgrids with V2G/EV charging go online in Washington and Maryland

LinkedIn
Twitter
Reddit
Facebook
Email

Microgrid projects in the US states of Washington and Maryland combining battery storage, solar and vehicle-grid integration have gone online.

Arlington Microgrid in Washington

Snohomish County PUD, a utility serving customers in Snohomish County and Camano Island, cut the ribbon on the Arlington Microgrid and Clean Energy Center last week (25 October), near Arlington Airport.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The project combines a 500kW solar PV array and a 1MW/1.4MWh lithium-ion battery energy storage system (BESS) and a pair of vehicle-to-grid (V2G) charging stations. The BESS is a PowerStore unit provided by Hitachi Energy, a wholly-owned subsidiary of the Japanese conglomerate Hitachi, formerly called Hitachi ABB Power Grids. Mitsubishi Electric provided the V2G charging infrastructure.

The project is focusing on combining the resources for disaster recovery, grid resiliency and electric vehicle integration. Specifically, it will go into islanding mode and provide power to the PUD’s Arlington Community Office during a grid outage (such as one caused by a wind storm or earthquake), a facility with a peak load of 150kW.

The PUD said that the project will demonstrate multiple uses of energy storage, provide a plan and design to study for future microgrid projects, and increase grid reliability in case of an emergency. The University of Washington will provide modelling, data analysis and reports on the project until 2033.

“The Arlington Microgrid provides a foundation for meeting both today’s emerging energy challenges and the future energy needs in Washington state and beyond,” said Antonio Verga, Hitachi Energy general manager of Grid Edge Solutions.

The utility purchased two Nissan Leaf EVs for the V2G part of the project. The Leaf is the only widely used consumer EV in the US market which is bidirectionally-capable.

The solar portion of the project is part of a community solar programme, and the PUD said that 500-plus of its customers reserved 100% of its available units in under a month, while 10% of the units were granted to two community service providers to benefit low-income households.

As shown in a design of the project below, it will connect to a Clean Energy Center which will host the microgrid controller and demonstrate the technology to help educate the public about new energy technologies. A solar PV tree is also on-site. The Center has a peak load of 50kW, highest on winter days due to heating requirements.

The PUD received US$3.5 million in funding from the Department of Commerce’s Clean Energy Fund to complete the project, which cost a total of US$12 million.

Pacific Northwest National Laboratory (PNNL) produced two reports assessing the lifetime cost-benefit of the V2G aspect of the microgrid. It looked at various factors which influence the economics of the technology, including battery cell degradation, replacement, roundtrip efficiencies, wholesale and
retail energy prices.

A PUD report said the PNNL’s study results indicated a strong correlation between the number of battery charge/discharge cycles and the cost of V2G.

The project also includes a 350kW backup diesel generator for when the BESS and solar array can no longer provide the islanding capabilities alone.

John Haarlow, PUD CEO/general manager, said: “Battery energy storage will help make critical infrastructure impervious to outages and help us meet energy demand when customer usage is at its highest. Vehicle-to-grid charging will allow us to work with homeowners and business owners to leverage EVs as backup or grid-assisted power sources.”

Read the University of Washington’s Techno-Economic Analysis of the Arlington Microgrid from February 2022 here.

Brookville Smart Energy Bus Depot in Maryland

In similar news, an EV charging station with a solar PV array, on-site BESS and microgrid controller allowing islanding mode was announced as operational yesterday (31 October).

The Brookville Smart Energy Bus Depot in Brookville, Maryland, will eventually power 70 electric buses belonging to the Brookville transit bus fleet, with 4.14MW of charging capacity.

It features a 3MW/4.3MWh energy storage system (ESS) from Dynapower which will store power to charge the electric buses during a grid outage, thus enabling the migrogrid capability. It also will also allow the Depot to participate in local utility Potomac Electric Power Company’s (Pepco) demand response programme.

How soon it will be charging 70 electric buses is not clear. 70 buses equates to half of the town’s bus fleet and Maryland as a state has a goal of 50% emissions-free buses by 2030.

A 1.6MW PV array and 1.9MW of diesel generators comprise the remaining power sources for the 6.5MW project.

Germany-headquartered firm The Mobility House is providing its ChargePilot software to optimise scheduling and the charging of the buses. The system coordinates with the charging capacity to source onsite power at the correct times throughout the day while ensuring that EV charging responds to load balancing and peak shaving commands from the microgrid controller.

Press releases from The Mobility House and Dynapower did not, however, go as far as saying that the microgrid will use vehicle-to-grid technology. Electrified buses hold a lot of potential for V2G technology thanks to larger battery sizes, more predictable schedules and a more consolidated pool of customers than the consumer EV space.

Public transit is a bit further behind when it comes to V2G participation than school buses. This is because they are out on the road a lot more and there are fewer bidirectionally-capable electric transit bus models. But, battery sizes typically 1.5-2 times bigger than a school bus and larger fleet sizes mean they also have significant potential as grid assets in the long run.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 28-29 March 2023 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

8 October 2024
San Francisco Bay Area, USA
PV Tech has been running an annual PV CellTech Conference since 2016. PV CellTech USA, on 8-9 October 2024 is our second PV CellTech conference dedicated to the U.S. manufacturing sector. The event in 2023 was a sell out success and 2024 will once again gather the key stakeholders from PV manufacturing, equipment/materials, policy-making and strategy, capital equipment investment and all interested downstream channels and third-party entities. The goal is simple: to map out PV manufacturing in the U.S. out to 2030 and beyond.
22 October 2024
New York, USA
Returning for its 11th edition, Solar and Storage Finance USA Summit remains the annual event where decision-makers at the forefront of solar and storage projects across the United States and capital converge. Featuring the most active solar and storage transactors, join us for a packed two-days of deal-making, learning and networking.
18 March 2025
Austin, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2025!
27 May 2025
London, UK
At the time of writing, Europe had had its most successful year in terms of Power Purchase Agreements (PPAs) with a record 7.8GW of renewable energy contracts signed. As we gather in May 2024 for the third edition of the Renewable Energy Revenues Summit, the energy landscape continues to evolve rapidly, influenced by the beating drum of climate change, volatility around power prices and the need to decarbonise power procurement as well as generation.
17 June 2025
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 17-18 June 2025, will be our fourth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2026 and beyond.
24 June 2025
London, UK
UK Solar Summit 2025 will look at the role solar currently plays in the energy mix, how this will change over the coming years and how this aligns with net-zero and other government targets. We will break down all these challenges and help build up solutions through discursive panels, motivational keynotes and case studies, with newly added interactive sessions to get you moving and meeting your peers, making the connections you need to boost your business.

Read Next

Premium
September 5, 2024
Georgia Power has secured a battery and equipment supply agreement (BESA) with Tesla for a 500MW/2,000MWh BESS portfolio made up of four projects of varying sizes under development by the investor-owned utility (IOU).
September 5, 2024
The energy storage system integration arm of Canadian utility Hydro-Québec, EVLO, will deploy 300MWh of battery energy storage systems (BESS) in Virginia, US.
September 5, 2024
Home battery storage aggregation projects have launched with participation of Tokyo Electric Power Co, and Tokyo Gas, two major utility companies in the Japanese capital.
September 5, 2024
The Q3 2024 edition of our downstream solar PV and energy storage journal, PV Tech Power, is now available to download.
September 4, 2024
Clean energy system integrator Ameresco and utility Southern California Edison (SCE) have agreed the substantial completion for two BESS projects out of a three-project order, though liquidated damages related to their substantial delay in coming online are still being negotiated.

Most Popular

Email Newsletter