Local authority approves 40MW UK ‘Energy Barn’ project for Green Hedge

September 4, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
Previous Green Hedge projects were sold to Anesco. Image: Anesco.

Green Hedge, a UK renewable energy developer that has diversified into battery energy storage systems, has had an application for a 40MW project approved by local authorities in Derbyshire, England.

Green Hedge, which has developed 200MW of renewables in Britain to date, mainly large-scale solar PV, netted £30 million (US$38.84 million) of funding towards battery storage projects from investor Zouk Capital in July. By that time, through a subsidiary company, Green Hedge Energy 2 Barn Ltd, the company had already in late May applied to South Derbyshire District Council, in England’s Midlands, for permission to construct the project.

According to the planning applications, the project would be a “40MW energy storage scheme (sui generis – ‘standalone’) to provide back up electricity services to the grid for a period of 25 years from the date of commission” of the battery storage project. The planned development is at Breach Farm, in Swadlincote, Derbyshire.

The area where the plant is to be built used to be coal-country. Indeed, the council warns that there may be “unrecorded coal mining hazards” in the vicinity of the plant. In contrast, a lack of hazardous waste, effluent or sewage expected from the energy storage facility, including a lack of noise, helped win the application, it seems. The dozens of blueprints and documents sent in to South Derbyshire Council make for interesting reading.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Green Hedge to retain ownership of future ‘Energy Barn’ projects

When announcing Zouk Capital’s £30 million investment back in July, Green Hedge said the money would be used to fuel expansion of the developer’s pipeline of ‘Energy Barns’, the brand name it has given to its large-scale lithium-ion battery energy storage projects, enclosed in steel-framed barns. At the moment, their chief purpose will be to provide frequency regulation services to UK transmission network operator (TNO) National Grid and bid into the capacity market, the mechanism for ensuring the network remains stable and ‘the lights stay on’ in Britain.

Having sold four 10MW systems to commercial energy solutions provider Anesco following a co-development deal in 2016, each backed with 15-year contracts in National Grid’s capacity market, Green Hedge said that going forward it expects to retain energy storage assets on its balance sheet, rather than sell them on.

The company claimed in July to have a 10.5GW pipeline of UK projects, for which it has applied for grid connections.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

Premium
March 5, 2026
Energy-Storage.news Premium speaks with Claire McConnell, VP business development for Redwood Materials’ energy storage business, Redwood Energy, about its recent backing from Google and Nvidia, and what it has planned next.
Premium
March 5, 2026
In this second part of our interview with Wood Mackenzie energy storage analysts, we look at risk factors and mitigation across the European and US markets.
Premium
March 4, 2026
We heard from Danske Commodities’ principal originator Rimshah Javed at the Energy Storage Summit 2026, to discuss trends in BESS offtake, optimisation, FCAs in Germany and the Danish market. The latter has taken off in the past year.
March 3, 2026
A second-round auction in the UK for grid stability services, including inertia, concluded without any wins for grid-forming battery energy storage system (BESS) projects.
March 3, 2026
Allianz GI, Luxcara and Return have acquired BESS projects and portfolios in Germany, Finland and Spain; Low Carbon, OX2, Cero Generation and Revera have taken FIDs on projects in Poland, Finland and the UK; and NHOA Energy has received a 600MWh order in Italy. All in all, the projects total at least 3.7GWh of capacity.