Sineng Electric passes whole-station-level grid-forming test in China

By Sineng Electric
October 17, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Sineng Electric, in close collaboration with the project owner and the Hunan Electric Test Research Institute (Hunan Xiangdian), has successfully completed a full-process grid-forming, grid-following and off-grid test at the Changsha Ningxiang Guanshan 100MW/200MWh energy storage power station, underlining that the company’s related technology has entered a new stage of large-scale global application.

As the first energy storage power station in Hunan Province equipped with grid-forming capability, the project is powered by Sineng’s new-generation 1250kW Central PCS and 5MW Central PCS MV turnkey station, featuring the company’s second-generation enhanced hybrid grid-forming technology.

Despite challenges including high on-site temperatures, tight schedules and complex multi-party coordination, the entire test campaign was completed within one week, its scope covering nine major categories—inertia response, primary frequency regulation, damping control, black-start, phase jump tolerance, active power control, grid voltage adaptability, continuous fault ride-through andthree-times overload capability.

From its self-developed grid-forming verification platform, hardware-in-the-loop simulation certification by CEPRI, and CQC full-unit certification, to station-level on site validation by a third-party (DNV), Sineng has become the first in the industry to achieve a full-stack “true grid-forming” verification loop.