Google files plan to power US$600m Vegas data centre with solar and batteries

January 9, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
A Google data centre in Oregon. Image: Flickr / Tony Webster.

Nevada utility NV Energy and Google are plotting a major solar-plus-storage facility outside of Las Vegas in a deal being billed as the largest battery-backed solar corporate agreement in the world.

The proposal was filed in December to Nevada’s Public Utilities Commission (PUC) by Nevada Power Co, a subsidiary of NV Energy.

While the length of the proposed power purchase agreement (PPA) and project load capacity were redacted from the public filing, market intelligence firm S&P Platts reported a 350MW solar plant backed by a 250-280MW battery storage system on Wednesday.

The energy will power Google’s US$600 million Henderson data centre near Las Vegas, which is scheduled to start operations in mid-2020.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

If approved, the solar-plus-storage facility would be commissioned by late 2023, according to the filings.

While construction of the renewables plant is underway, the agreement stipulates that NV Energy will provide Google with wholesale market energy “priced at an appropriate index pricing” or with capacity from other NV Energy generators.

Once the solar-plus-storage plant is live, NV Energy will have the right to buy any excess power back from Google.

In early December, the utility – a near-monopoly in Nevada – secured approval from the PUC for a 1GW+ trio of solar projects that would be collectively backed by 590MW of storage. Those plants are set to come online by 2024 and are being developed by 8minute Solar Energy, EDF Renewables and a Quinbrook Infrastructure Partners – Arevia Power partnership.

NV Energy is a subsidiary of Berkshire Hathaway group, the conglomerate run by Warren Buffett that owns Duracell, Fruit of the Loom, Dairy Queen and parts of Kraft Heinz Company and American Express.

A prehearing conference for the Google power procurement deal will be held on 23 January.

This article first appeared on PV Tech.

Read Next

March 16, 2026
A 500MW/1,000MWh battery energy storage system (BESS) with grid-forming inverters has gone into commercial operation in Cambodia.
Premium
March 16, 2026
Hamilton Locke partner Matt Baumgurtel warns of a seismic shift as distributed energy resources with “zero marginal cost” emerge.
March 13, 2026
Google has finalised its acquisition of US renewable energy developer Intersect Power, as part of its plan to power its data centre expansions in the US.
March 13, 2026
Iron flow battery company ESS Tech Inc highlighted its recent partnership with Google and the acquisition of VoltStorage GmbH, as profitability remained out of reach in 2025.
March 12, 2026
In this US news roundup, we have financing updates for GridStor, Arevon, and Primergy, related to energy storage projects in Texas, California, and Nevada, respectively.