After failing to obtain local approval for the construction of a 250MW/1,000MWh standalone battery energy storage system (BESS) in the Californian city of San Juan Capistrano, Engie is pursuing state approval via the California Energy Commission (CEC) as permitted under Assembly Bill (AB) 205.

The legislation, signed into law by California Governor Gavin Newsom in June 2022, contained several new measures to increase the CEC’s siting authority over specific grid-connected facilities, including battery storage facilities larger than 200MWh in size.

Engie rezoning request denied

The City of San Juan Capistrano was initially introduced to the Compass Energy Storage project in March 2021 after Broad Reach Power (BRP) – now a wholly-owned subsidiary of Engie – submitted a pre-application review of the facility with the city’s Development Services Department.

Saddleback Church, the landowner for the proposed project, filed a rezoning request with city officials in September 2022 which, if granted, would have allowed the developer to obtain a Conditional Use Permit (CUP) for the battery project.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, progress on the project was seemingly halted after city officials denied the church’s request in November 2022. This was followed by Engie officially withdrawing its application with the city of San Juan Capistrano in February 2024.

In amongst all this, BRP and its entire project pipeline became part of Engie after the French multinational energy company finalised its acquisition of the utility-scale energy storage developer from funds owned by EnCap and Apollo in October 2023, as reported in Energy-Storage.News.

According to Engie’s 2023 annual report, the acquisition included 350MW in operating assets, 880MW of under-construction assets with an expected online date in 2024 and a further 1.7GW longer-term development pipeline across California, Texas and other central areas within the United States.

Objection to CEC jurisdiction

Following Engie’s recent April 2024 application with the California regulator asking for approval of its proposed Compass battery storage project, officials at the city of San Juan Capistrano have spoken out against the CEC’s jurisdiction over the project.

In a 31 May filing lodged with the CEC, city officials argue that AB 205 was not enacted to give developers a “second bite of the apple”, and accuse the developer of looking for “a more favourable project decision” after it was denied through the local planning process.

The CEC online docket used by the regulator to house Engie’s application has also attracted over 100 comment filings from locals with the majority of these opposing the project.

Once the CEC deems Engie’s application complete, it will have 270 days to prepare an environmental impact report (EIR) for the proposed development and make a final decision on whether the project can move forward at a public meeting.

Temporary battery storage moratorium

On 7 May 2024, San Juan Capistrano officials enacted a temporary ordinance prohibiting the development of new battery storage facilities within the city until next April.

According to the ordinance, officials will use the time to “explore adjustments to the City’s General Plan and Zoning Regulations to mitigate the safety risks associated with BESS facilities.” The introduction of the temporary moratorium does not prevent Engie from permitting the Compass project with the CEC, however.

The Compass battery project will utilise lithium iron phosphate (LFP) battery technology and connect to the CAISO grid via San Diego Gas & Electric’s (SDG&E’s) Trabuco – Capistrano 138kV transmission line.

An interconnection agreement for the project has already been secured under the queue request named “Captive Energy Storage” (queue no. 1806).

Intersect Power also goes CEC route for solar-battery-hydrogen project planned with 4.6GWh BESS

Similar to Engie, clean energy company Intersect Power has also chosen to obtain planning permission for one of its renewable developments, known as the Darden Project, through the CEC rather than through the more traditional local route.

Intersect Power’s proposed Darden facility will consist of an up to 1,150MW behind-the-meter solar farm and 4.6GWh BESS hooked up to a 1,150MW green hydrogen generation facility in Fresno County, California.

As reported in Energy-Storage.News, Intersect Power recently brought online its Oberon Solar and Storage project (pictured above) which comprises a 679MWp/500MWac solar PV facility paired with a 250MW/1,000MWh BESS located in Riverside County, California.

Read Next

February 25, 2026
Germany’s energy storage market growth will be hampered by a regulatory decision to potentially charge utility-scale project operators fees for use of the grid, Energy-Storage.news has heard.
February 25, 2026
In this Energy-Storage.news roundup, FlexGen updates its EMS, LandGate launches a BESS site selection tool, ON.energy and Shoals target AI data centres, and Sunrun has a successful season of dispatching energy with PG&E.
February 25, 2026
The 200MW/400MWh New England battery energy storage system (BESS) in New South Wales has registered with the Australian Energy Market Operator’s (AEMO) Market Management System (MMS).
February 24, 2026
Wooderson Solar Development Co has secured federal environmental approval for a 450MW solar PV power plant with 3,600MWh of co-located battery energy storage in Queensland, Australia.
February 19, 2026
In this US news roundup, CC Power signs an agreement with Hydrostor for 400MWh of its Willow Rock LDES project, PowerSecure builds microgrids in New Mexico, and ESS Inc acquires VoltStorage.