E.ON claims energy storage world first with large-scale modular battery M5BAT

LinkedIn
Twitter
Reddit
Facebook
Email

Inverter manufacturer SMA Solar Technology supplied technical components, along with a division of battery company Exide. Image: SMA.
Construction has begun on what is claimed to be the world’s first modular large-scale battery storage system, a 5MW device at a research university in Aachen, Germany.

The Modular, Multi-megawatt, Multi-technology Medium Voltage Battery Storage System, handily abbreviated to M5BAT, is being built at the technical institute RWTH Aachen University. It will assess and demonstrate the appropriateness of combining a number of different battery types into one system.

The project seeks to further the integration of renewable energy into electricity networks, while it is also hoped that increased modularity will allow the system to be applied to a broader range of uses than existing large-scale battery storage devices.

Backed by the German Federal ministry of economic affairs and the environment with €6.7 million funding through a grant, the project involves researchers from RWTH Aachen University and the research centre of multi-national utility company E.ON. Also involved are the GNB Industrial Power unit of battery maker Exide Technologies, E.ON itself and solar inverter manufacturer SMA Solar Technology.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

GNB Industrial Power and SMA will supply technical components, as might be expected. The system will be built into a two-storey facility, covering around 500m2 of a former office building converted to its new purpose by E.ON. E.ON Energy Research Centre will assemble the batteries, with the system scheduled for completion in mid-2016.

Utility pressure

Several US utility companies have started procuring storage in ever-greater capacities, especially in regions driven by mandates such as California or Puerto Rico, or states where a conscious shift at the top level to distributed energy systems has begun, such as New York, or again California. Their European counterparts have not been as quick for the most part, with a number of high profile trials – such as the UK’s 6MW ‘Big Battery’ – and the operation of large-scale storage on the frequency regulation market in Germany.

E.ON appears however to have a fairly pro-active stance on the changing nature of energy, last year announcing a full split of its business units into two, one dealing with its conventional fossil fuels business and the other dealing with new and renewable energies. One energy storage and renewable energy industry insider who wished to remain anonymous did comment at the time that the utility was “running scared” at the speed of change towards distributed generation of non-fossil fuel energy, however a request for interview with E.ON to discuss the claim was declined at the time. In the past few weeks, the head of the company’s US operations has also publicly urged the rest of the energy industry to “embrace” president Barack Obama’s EPA Clean Power Plan.

Meanwhile, modularity of battery systems is becoming an ever-bigger question for the industry. Sizing batteries to meet the different needs of each region and application can be both expensive and tricky. One German manufacturer known primarily for its energy storage systems, ASD Sonnenspeicher, claims that with a new system that it has developed called Pacadu, batteries of different type and size can be neatly put into parallel circuits. This could open up the promise of scale and convenience for grid network operators and storage project developers, while seemingly pitting ASD in direct competition with SMA and its partners on the M5BAT project.

Utility E.ON and its energy research division announced the start of construction on Wednesday. This image and cropped cover image: E.On.

Read Next

October 8, 2025
The NSW Independent Planning Commission has granted planning approval for Potentia Energy’s 500MW Tallawang solar-plus-storage project.
October 3, 2025
EDF Renewables has brought its 300MWh Milagro project online in New Mexico, while Enlight Renewable Energy has secured US$340 million in tax equity financing for its 940MWh Roadrunner project in Arizona.
October 2, 2025
The TSO of Italy has completed its first MACSE auctions for energy storage, procuring 10GWh of capacity at what the NHOA CEO called ‘exceptionally competitive prices’.
September 30, 2025
According to the Q3 2025 US Energy Storage Monitor from Wood Mackenzie Power & Renewables and the American Clean Power Association (ACP), annual installations will not reach 2025 levels again until 2029.
September 29, 2025
Samsung C&T Renewable Energy Australia has submitted plans for a 300MWh solar-plus-storage project in Queensland to Australia’s EPBC Act.

Most Popular

Email Newsletter