DC Circuit Court of Appeals upholds FERC plan to speed up permitting for US energy projects’ grid interconnection

LinkedIn
Twitter
Reddit
Facebook
Email

A US court has upheld a Federal Energy Regulatory Commission (FERC) plan to speed up the permitting process for connecting energy projects to the grid.

FERC Order No. 2023 was challenged in the DC Circuit Court of Appeals by several grid operators and utilities. However, on Friday 31 July, the court upheld the order.

The order was introduced in 2023 and sought to address the huge interconnection queue backlog of projects waiting to connect to US power grids, almost all of which were solar PV, wind power and energy storage projects. Data shows that there was around 2,600GW of energy project capacity in US interconnection queues at the end of 2023.

It proposes replacing the first-come, first-served system with a requirement for operators to assess projects in clusters and award connection places based on readiness, along with greater transparency and survey requirements. It also raises the financial and other commitments that generators must make to enter and remain in the queue.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“This is a win for ratepayers, competition, and the environment. It will help speed interconnection processes and unlock cheaper, cleaner energy that has been waiting years to connect to the grid,” said Alexander Tom, attorney for Earthjustice who argued the case before the DC Circuit Court of Appeals.

The grid operators and utilities that opposed the order said that fines for late interconnection studies were too steep and overstepped FERC’s legal bounds, arguing that the regulator had not successfully proven that the interconnection delays were the fault of grid operators. The court’s three-judge panel disagreed.

Since the initial order was proposed in 2023, projected US power demand has increased as a result of AI data centre expansion and greater electrification. A better interconnection queue process could force operators to meet growing demand more effectively, and with the backlog of renewable energy projects that have been stranded in queues.

To read the full version of this story, visit PV Tech, where it first appeared.

Read Next

August 26, 2026
In this news roundup, Eos and WATTMORE; Gotion and Gamma Technologies; Middle River Power and PowerTransitions; and Electra AI and MinTech are advancing battery energy storage system (BESS) technology in the US.
Premium
August 19, 2026
The grid-scale energy storage market in Germany is in a strong position but key questions around grid fees, grid connections, FCAs and the upcoming capacity market remain, speakers at the upcoming Energy Storage Summit Germany 2026 said. 
August 12, 2026
EPEC Group has been awarded a contract to cover the high-voltage connection works for the Lower Wonga Solar Farm in Queensland, Australia, by the EPC contractor INTEC Energy Solutions.
July 30, 2026
IPP Eolian has begun construction on Flint Grid, a 200MW/1.06GWh energy storage project in Jersey Township, Licking County, Ohio, US.
July 28, 2026
There can be great value in co-location, but the operational reality is not as simple as it may sound, writes Daniel Moore-Oats of Arenko.