Ameresco and SCE agree completion for two of three California BESS projects, liquidated damages still loom

September 4, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Clean energy system integrator Ameresco and utility Southern California Edison (SCE) have agreed on damages to be paid for two battery energy storage system (BESS) projects out of a three-project order, though liquidated damages related to a substantial delay in commissioning are still being negotiated.

SCE will pay Ameresco approximately US$110 million within seven days for the milestone completion of the BESS projects. However, this reflects a set-off of liquidated damages, which are still in dispute, as well as additional work costs.

Final acceptance payments will follow upon the projects’ completion. The third and final project in the order is expected to reach substantial completion in Q4 2024.

Energy-Storage.news first reported that SCE was considering withholding liquidated damages from Ameresco in July this year (Premium access article).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The projects totalling 537.5MW/2,150MWh were meant to come online in August 2022 but have been delayed by over two years. The contract value for Ameresco was US$1.226 billion.

Ameresco issued SCE with a ‘force majeure’ claim in 2022, citing the shutdown of factories in Beijing due to Covid-19 lockdowns.

The projects are located at three distribution-level substation parcels in SCE’s service territory to provide for the electricity demands in the San Joaquin Valley, the Long Beach area and Rancho Cucamonga and nearby communities. They were specifically procured in light of emergency reliability risks due to extended drought, wildfire and heatwaves in California.

In other BESS activity, Ameresco recently completed 313MWh of projects for a utility in Colorado and landed its first job in the UK, a 624MWh project for developer Atlantic Green.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 25, 2026
American Battery Factory (AFB) has secured offtake agreements for 4.5GWh of its initial 5.5GWh US factory output.
Premium
March 25, 2026
As battery energy storage systems (BESS) and electric vehicle (EV) infrastructure expand in the US and Europe, a clear contrast is becoming evident in their market growth.
March 24, 2026
Arevon, Banpu Power (BPP) and Energy Vault have made BESS project announcements totalling 1,550MWh of capacity in the US.
March 24, 2026
The legislative body of Nebraska, US, has advanced a bill to clarify and expand the state’s use of battery energy storage systems (BESS).
March 23, 2026
The New Jersey Board of Public Utilities (NJBPU) has selected developer and IPP Elevate Renewables’ 600MWh battery energy storage system (BESS) for development in Ridgefield, New Jersey, US.